Original Cost
₹4147 Cr
Baseline estimate
Revised Cost
₹4147 Cr
Latest approved cost
Expenditure
₹225 Cr
Spent to date
Utilization
5.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹3922 Cr
Budget left
Spent
₹225 Cr
Remaining
₹3922 Cr
Total
₹4147 Cr
Project Approved
Construction / Implementation
Original End Date
25/03/2028
Revised Completion
Completed
Project is within original budget of ₹4147 Cr — no cost escalation recorded.
Expenditure stands at ₹225 Cr, which is 5.4% of the revised project cost.
Remaining budget: ₹3922 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Coal.