Original Cost
₹218 Cr
Baseline estimate
Revised Cost
₹218 Cr
Latest approved cost
Expenditure
₹170 Cr
Spent to date
Utilization
78.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹48 Cr
Budget left
Spent
₹170 Cr
Remaining
₹48 Cr
Total
₹218 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/12/2025
Completed
Project is within original budget of ₹218 Cr — no cost escalation recorded.
Expenditure stands at ₹170 Cr, which is 78.0% of the revised project cost.
Remaining budget: ₹48 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Coal.