Environmental ClearanceForest Clearance

Construction of 4 – laning of Masrakh to Chakia ( Km 86 to Km 143 of NH – 227A ) and Chakia to Bhitha more (Km 0 to Km 104 of old NH – 104(New NH- 227)) section of Ramjanki Marg in the state of Bihar. (Forest Division Motihari = chainage km 19+400 to67+185 And 71+825 to 76+650)

Purba Champaran, BiharExecutive Engineer
Proposal no.FP/BR/ROAD/595183/2026

Current status

Pending at DFO for Scrutiny and Recommendation

Updated 13 Oct 2026

Project cost
₹5,928 Cr
As filed on PARIVESH
Land required
262.42 Ha
Total project area
Submitted
13 Oct 2026
Filed on PARIVESH
Documents
2
PDF & KML files

About this proposal

Overview

Construction of 4 – laning of Masrakh to Chakia ( Km 86 to Km 143 of NH – 227A ) and Chakia to Bhitha more (Km 0 to Km 104 of old NH – 104(New NH- 227)) section of Ramjanki Marg in the state of Bihar. (Forest Division Motihari = chainage km 19+400 to67+185 And 71+825 to 76+650) is a Forest Clearance (FC) proposal filed under India's PARIVESH portal, tracked here as part of BiharInfraTales' Bihar clearance monitoring dashboard. The proposal (reference number FP/BR/ROAD/595183/2026) was submitted by Anuj Kumar on behalf of Executive Engineer in Purba Champaran, Bihar, with an estimated project cost of ₹5,928.28 crore spread over 262.42 hectares.

The proposal falls under the Forestry / Linear sector and currently carries the status "Pending at DFO for Scrutiny and Recommendation". Forest Clearance is required under the Forest (Conservation) Act for diversion of forest land for non-forest infrastructure and development purposes, governed by the Ministry of Environment, Forest and Climate Change (MoEFCC) and state forest departments.

The application was submitted on 2026-10-13. The land requirement comprises 0.7504 ha of forest land and 261.6732 ha of non-forest land. Full proposal documents, boundary (KML) data, and the exact project location, where published by PARIVESH, are linked on this page. This record is updated as the clearance moves through verification, appraisal, and the final grant or rejection stage.

PARIVESH data

Proposal record

10 fields
Proposal Number
FP/BR/ROAD/595183/2026
Organisation
Executive Engineer
Applicant
Anuj Kumar
Clearance Type
Forest Clearance
Proposal Type
FC
Current Status
Pending at DFO for Scrutiny and Recommendation
Submission Date
2026-10-13
Shape of Project
Linear
Forest Land
0.7504 Ha
Non-Forest Land
261.6732 Ha

Where

Project location

3 fields
District
Purba Champaran
State
Bihar
Total Land Area
262.42 Ha

Source files

Documents & boundary data

2 files

Data from the Government of India's PARIVESH environmental clearance portal.

Questions

Frequently asked questions

1What is the Environmental Clearance status of "Construction of 4 – laning of Masrakh to Chakia ( Km 86 to Km 143 of NH – 227A )"?

As per the latest PARIVESH data, proposal FP/BR/ROAD/595183/2026 carries the status "Pending at DFO for Scrutiny and Recommendation". It is a infrastructure-sector project in Purba Champaran, Bihar.

2Who is the applicant for this Environmental Clearance proposal?

The proposal was filed by Anuj Kumar on behalf of Executive Engineer. The clearance type is Forest Clearance and it is tracked under PARIVESH reference FP/BR/ROAD/595183/2026.

3What is the project cost and land requirement?

The proposal reports an estimated cost of ₹5,928 Cr and requires 262.42 Ha of land (0.7504 ha forest, 261.6732 ha non-forest).

4What is Environmental Clearance (EC) and why does this project need it?

Environmental Clearance is a mandatory approval under India's Environment Impact Assessment (EIA) framework, granted by the MoEFCC or the State Environment Impact Assessment Authority (SEIAA) via the PARIVESH portal. Projects that can significantly affect the environment must obtain EC — covering appraisal of pollution, land use, and ecological impact — before construction or expansion can lawfully begin.