Environmental ClearanceForest Clearance

Construction of ROB & its approaches in between Dumraon & Baruna Rly. Stn. in lieu of L.C. No. 67/A in Dumraon - Bhojpur Road of Buxar District

Buxar, BiharBihar state road development corporation limited
Proposal no.FP/BR/ROAD/539324/2025

Current status

Final Diversion Order Issued

Updated 6 Oct 2026

Project cost
₹57.45 Cr
As filed on PARIVESH
Land required
1.23 Ha
Total project area
Submitted
13 Nov 2025
Filed on PARIVESH
Documents
2
PDF & KML files

About this proposal

Overview

Construction of ROB & its approaches in between Dumraon & Baruna Rly. Stn. in lieu of L.C. No. 67/A in Dumraon - Bhojpur Road of Buxar District is a Forest Clearance (FC) proposal filed under India's PARIVESH portal, tracked here as part of BiharInfraTales' Bihar clearance monitoring dashboard. The proposal (reference number FP/BR/ROAD/539324/2025) was submitted by Sri Saket Kumar on behalf of Bihar state road development corporation limited in Buxar, Bihar, with an estimated project cost of ₹57.45 crore spread over 1.23 hectares.

The proposal falls under the Forestry / Linear sector and currently carries the status "Final Diversion Order Issued". Forest Clearance is required under the Forest (Conservation) Act for diversion of forest land for non-forest infrastructure and development purposes, governed by the Ministry of Environment, Forest and Climate Change (MoEFCC) and state forest departments.

The application was submitted on 2025-11-13. The land requirement comprises 0.995 ha of forest land and 0.235 ha of non-forest land. Stage-I approval on 09-FEB-2026, Stage-II approval on 20-AUG-2026. Full proposal documents, boundary (KML) data, and the exact project location, where published by PARIVESH, are linked on this page. This record is updated as the clearance moves through verification, appraisal, and the final grant or rejection stage.

PARIVESH data

Proposal record

13 fields
Proposal Number
FP/BR/ROAD/539324/2025
Organisation
Bihar state road development corporation limited
Applicant
Sri Saket Kumar
Clearance Type
Forest Clearance
Proposal Type
FC
Current Status
Final Diversion Order Issued
Submission Date
2025-11-13
Stage-I Approval Date
09-FEB-2026
Stage-II Approval Date
20-AUG-2026
Nodal Accepted Date
22-NOV-2025
Shape of Project
Linear
Forest Land
0.995 Ha
Non-Forest Land
0.235 Ha

Where

Project location

3 fields
District
Buxar
State
Bihar
Total Land Area
1.23 Ha

Source files

Documents & boundary data

2 files

Data from the Government of India's PARIVESH environmental clearance portal.

Questions

Frequently asked questions

1What is the Environmental Clearance status of "Construction of ROB & its approaches in between Dumraon & Baruna Rly. Stn. in li"?

As per the latest PARIVESH data, proposal FP/BR/ROAD/539324/2025 carries the status "Final Diversion Order Issued". It is a infrastructure-sector project in Buxar, Bihar.

2Who is the applicant for this Environmental Clearance proposal?

The proposal was filed by Sri Saket Kumar on behalf of Bihar state road development corporation limited. The clearance type is Forest Clearance and it is tracked under PARIVESH reference FP/BR/ROAD/539324/2025.

3What is the project cost and land requirement?

The proposal reports an estimated cost of ₹57.45 Cr and requires 1.23 Ha of land (0.995 ha forest, 0.235 ha non-forest).

4What is Environmental Clearance (EC) and why does this project need it?

Environmental Clearance is a mandatory approval under India's Environment Impact Assessment (EIA) framework, granted by the MoEFCC or the State Environment Impact Assessment Authority (SEIAA) via the PARIVESH portal. Projects that can significantly affect the environment must obtain EC — covering appraisal of pollution, land use, and ecological impact — before construction or expansion can lawfully begin.