- Project cost
- ₹0.80 Cr
- As filed on PARIVESH
- Land required
- 0.02 Ha
- Total project area
- Submitted
- 24 May 2026
- Filed on PARIVESH
- Documents
- 1
- PDF & KML files
About this proposal
Overview
Diversion of 0.019125 ha of forest land for construction of approach road for opening retail outlet of M/s Bharat Petroleum Corporation Ltd. on Khata No.-244, 1741, Khesra No.-4720, 4721, Thana No.-627, Mauza-Balia Lakhminia, Thana-Balia to Mungerghat-Rashidpur Road Road in Begusarai district of Bihar. is a Forest Clearance (FC) proposal filed under India's PARIVESH portal, tracked here as part of BiharInfraTales' Bihar clearance monitoring dashboard. The proposal (reference number FP/BR/PetrolPump/580011/2026) was submitted by punam kumari on behalf of punam kumari in Begusarai, Bihar, with an estimated project cost of ₹0.8 crore spread over 0.02 hectares.
The proposal falls under the Forestry / Linear sector and currently carries the status "Delisted_by_system". Forest Clearance is required under the Forest (Conservation) Act for diversion of forest land for non-forest infrastructure and development purposes, governed by the Ministry of Environment, Forest and Climate Change (MoEFCC) and state forest departments.
The application was submitted on 2026-05-24. The land requirement comprises 0.0191 ha of forest land and 0 ha of non-forest land. Full proposal documents, boundary (KML) data, and the exact project location, where published by PARIVESH, are linked on this page. This record is updated as the clearance moves through verification, appraisal, and the final grant or rejection stage.
PARIVESH data
Proposal record
- Proposal Number
- FP/BR/PetrolPump/580011/2026
- Organisation
- punam kumari
- Applicant
- punam kumari
- Clearance Type
- Forest Clearance
- Proposal Type
- FC
- Current Status
- Delisted_by_system
- Submission Date
- 2026-05-24
- Nodal Accepted Date
- 24-MAY-2026
- Shape of Project
- Linear
- Forest Land
- 0.0191 Ha
- Non-Forest Land
- 0 Ha
Where
Project location
- District
- Begusarai
- State
- Bihar
- Total Land Area
- 0.02 Ha
Source files
Documents & boundary data
Data from the Government of India's PARIVESH environmental clearance portal.
Questions
Frequently asked questions
1What is the Environmental Clearance status of "Diversion of 0.019125 ha of forest land for construction of approach road for op"?
As per the latest PARIVESH data, proposal FP/BR/PetrolPump/580011/2026 carries the status "Delisted_by_system". It is a infrastructure-sector project in Begusarai, Bihar.
2Who is the applicant for this Environmental Clearance proposal?
The proposal was filed by punam kumari on behalf of punam kumari. The clearance type is Forest Clearance and it is tracked under PARIVESH reference FP/BR/PetrolPump/580011/2026.
3What is the project cost and land requirement?
The proposal reports an estimated cost of ₹0.80 Cr and requires 0.02 Ha of land (0.0191 ha forest, 0 ha non-forest).
4What is Environmental Clearance (EC) and why does this project need it?
Environmental Clearance is a mandatory approval under India's Environment Impact Assessment (EIA) framework, granted by the MoEFCC or the State Environment Impact Assessment Authority (SEIAA) via the PARIVESH portal. Projects that can significantly affect the environment must obtain EC — covering appraisal of pollution, land use, and ecological impact — before construction or expansion can lawfully begin.