Environmental ClearanceForest Clearance

Diversion of 0.01725 ha of forest land for construction of approach road for opening retail outlet of IOCL on Khata No.-16(New), 2(Old), Khesra No.-61, Thana No.-672, Thana-Rafiganj, Mauza-English to SH-68 Rafiganj(Kasima More)-Sheoganj Road in Aurangabad district of Bihar.

Aurangabad, BiharSANJAY KUMAR
Proposal no.FP/BR/PetrolPump/575816/2026

Current status

Pending at UA for Compensatory Levies Payment and Compliance Report

Updated 6 Oct 2026

Project cost
₹0.60 Cr
As filed on PARIVESH
Land required
0.02 Ha
Total project area
Submitted
29 May 2026
Filed on PARIVESH
Documents
0
None published yet

About this proposal

Overview

Diversion of 0.01725 ha of forest land for construction of approach road for opening retail outlet of IOCL on Khata No.-16(New), 2(Old), Khesra No.-61, Thana No.-672, Thana-Rafiganj, Mauza-English to SH-68 Rafiganj(Kasima More)-Sheoganj Road in Aurangabad district of Bihar. is a Forest Clearance (FC) proposal filed under India's PARIVESH portal, tracked here as part of BiharInfraTales' Bihar clearance monitoring dashboard. The proposal (reference number FP/BR/PetrolPump/575816/2026) was submitted by Sanjay Kumar on behalf of SANJAY KUMAR in Aurangabad, Bihar, with an estimated project cost of ₹0.6 crore spread over 0.02 hectares.

The proposal falls under the Forestry / Linear sector and currently carries the status "Pending at UA for Compensatory Levies Payment and Compliance Report". Forest Clearance is required under the Forest (Conservation) Act for diversion of forest land for non-forest infrastructure and development purposes, governed by the Ministry of Environment, Forest and Climate Change (MoEFCC) and state forest departments.

The application was submitted on 2026-05-29. The land requirement comprises 0.0172 ha of forest land and 0 ha of non-forest land. Stage-I approval on 14-JUL-2026. Full proposal documents, boundary (KML) data, and the exact project location, where published by PARIVESH, are linked on this page. This record is updated as the clearance moves through verification, appraisal, and the final grant or rejection stage.

PARIVESH data

Proposal record

12 fields
Proposal Number
FP/BR/PetrolPump/575816/2026
Organisation
SANJAY KUMAR
Applicant
Sanjay Kumar
Clearance Type
Forest Clearance
Proposal Type
FC
Current Status
Pending at UA for Compensatory Levies Payment and Compliance Report
Submission Date
2026-05-29
Stage-I Approval Date
14-JUL-2026
Nodal Accepted Date
29-MAY-2026
Shape of Project
Linear
Forest Land
0.0172 Ha
Non-Forest Land
0 Ha

Where

Project location

3 fields
District
Aurangabad
State
Bihar
Total Land Area
0.02 Ha

Source files

Documents & boundary data

No clearance documents or boundary (KML) files have been published for this proposal yet. See the Bihar EC Monitoring dashboard for the interactive map and every other proposal.

Data from the Government of India's PARIVESH environmental clearance portal.

Questions

Frequently asked questions

1What is the Environmental Clearance status of "Diversion of 0.01725 ha of forest land for construction of approach road for ope"?

As per the latest PARIVESH data, proposal FP/BR/PetrolPump/575816/2026 carries the status "Pending at UA for Compensatory Levies Payment and Compliance Report". It is a infrastructure-sector project in Aurangabad, Bihar.

2Who is the applicant for this Environmental Clearance proposal?

The proposal was filed by Sanjay Kumar on behalf of SANJAY KUMAR. The clearance type is Forest Clearance and it is tracked under PARIVESH reference FP/BR/PetrolPump/575816/2026.

3What is the project cost and land requirement?

The proposal reports an estimated cost of ₹0.60 Cr and requires 0.02 Ha of land (0.0172 ha forest, 0 ha non-forest).

4What is Environmental Clearance (EC) and why does this project need it?

Environmental Clearance is a mandatory approval under India's Environment Impact Assessment (EIA) framework, granted by the MoEFCC or the State Environment Impact Assessment Authority (SEIAA) via the PARIVESH portal. Projects that can significantly affect the environment must obtain EC — covering appraisal of pollution, land use, and ecological impact — before construction or expansion can lawfully begin.