Environmental ClearanceForest Clearance

Diversion of 0.021 ha of forest land for construction of approach road for opening retail outlet of IOCL on Khata No.-439 Plot No.-92, Thana No.-66, Mauza-Mohanpur Karja, Thana-Barhara to Ara - Barhara Road in Bhojpur (Ara) district of Bihar

Bhojpur, Biharsurendar ray
Proposal no.FP/BR/PetrolPump/571511/2026

Current status

Pending at UA for Compliance Report

Updated 6 Oct 2026

Project cost
₹0.80 Cr
As filed on PARIVESH
Land required
0.02 Ha
Total project area
Submitted
6 Mar 2026
Filed on PARIVESH
Documents
2
PDF & KML files

About this proposal

Overview

Diversion of 0.021 ha of forest land for construction of approach road for opening retail outlet of IOCL on Khata No.-439 Plot No.-92, Thana No.-66, Mauza-Mohanpur Karja, Thana-Barhara to Ara - Barhara Road in Bhojpur (Ara) district of Bihar is a Forest Clearance (FC) proposal filed under India's PARIVESH portal, tracked here as part of BiharInfraTales' Bihar clearance monitoring dashboard. The proposal (reference number FP/BR/PetrolPump/571511/2026) was submitted by surendar ray on behalf of surendar ray in Bhojpur, Bihar, with an estimated project cost of ₹0.8 crore spread over 0.02 hectares.

The proposal falls under the Forestry / Linear sector and currently carries the status "Pending at UA for Compliance Report". Forest Clearance is required under the Forest (Conservation) Act for diversion of forest land for non-forest infrastructure and development purposes, governed by the Ministry of Environment, Forest and Climate Change (MoEFCC) and state forest departments.

The application was submitted on 2026-03-06. The land requirement comprises 0.021 ha of forest land and 0 ha of non-forest land. Stage-I approval on 09-SEP-2026. Full proposal documents, boundary (KML) data, and the exact project location, where published by PARIVESH, are linked on this page. This record is updated as the clearance moves through verification, appraisal, and the final grant or rejection stage.

PARIVESH data

Proposal record

12 fields
Proposal Number
FP/BR/PetrolPump/571511/2026
Organisation
surendar ray
Applicant
surendar ray
Clearance Type
Forest Clearance
Proposal Type
FC
Current Status
Pending at UA for Compliance Report
Submission Date
2026-03-06
Stage-I Approval Date
09-SEP-2026
Nodal Accepted Date
06-MAR-2026
Shape of Project
Linear
Forest Land
0.021 Ha
Non-Forest Land
0 Ha

Where

Project location

3 fields
District
Bhojpur
State
Bihar
Total Land Area
0.02 Ha

Source files

Documents & boundary data

2 files

Data from the Government of India's PARIVESH environmental clearance portal.

Questions

Frequently asked questions

1What is the Environmental Clearance status of "Diversion of 0.021 ha of forest land for construction of approach road for openi"?

As per the latest PARIVESH data, proposal FP/BR/PetrolPump/571511/2026 carries the status "Pending at UA for Compliance Report". It is a infrastructure-sector project in Bhojpur, Bihar.

2Who is the applicant for this Environmental Clearance proposal?

The proposal was filed by surendar ray on behalf of surendar ray. The clearance type is Forest Clearance and it is tracked under PARIVESH reference FP/BR/PetrolPump/571511/2026.

3What is the project cost and land requirement?

The proposal reports an estimated cost of ₹0.80 Cr and requires 0.02 Ha of land (0.021 ha forest, 0 ha non-forest).

4What is Environmental Clearance (EC) and why does this project need it?

Environmental Clearance is a mandatory approval under India's Environment Impact Assessment (EIA) framework, granted by the MoEFCC or the State Environment Impact Assessment Authority (SEIAA) via the PARIVESH portal. Projects that can significantly affect the environment must obtain EC — covering appraisal of pollution, land use, and ecological impact — before construction or expansion can lawfully begin.