Environmental ClearanceForest Clearance

1200 MW Gosaintari Pumped Storage Project

Nawada, BiharSUn Hydro Energy Private LIMITED
Proposal no.FP/BR/HYD/IRRIG/591169/2026

Current status

Pending at UA due to EDS by MS after PSC-I
  1. SubmittedApplication filed on PARIVESH
  2. VerificationChecked for completeness
  3. 3ExaminationNowScrutiny; shortfalls raised as EDS
  4. 4Expert appraisalAppraised by the expert committee (SEAC/EAC)
  5. 5DecisionClearance granted or refused

Updated 6 Oct 2026

Project cost
₹6,198 Cr
As filed on PARIVESH
Land required
282.97 Ha
Total project area
Submitted
7 Sep 2026
Filed on PARIVESH
Documents
3
PDF & KML files

About this proposal

Overview

1200 MW Gosaintari Pumped Storage Project is a Forest Clearance (FC) proposal filed under India's PARIVESH portal, tracked here as part of BiharInfraTales' Bihar clearance monitoring dashboard. The proposal (reference number FP/BR/HYD/IRRIG/591169/2026) was submitted by Amol Suryabhan Chikte on behalf of SUn Hydro Energy Private LIMITED in Nawada, Bihar, with an estimated project cost of ₹6,198 crore spread over 282.97 hectares.

The proposal falls under the Forestry / Linear sector and currently carries the status "Pending at UA due to EDS by MS after PSC-I". Forest Clearance is required under the Forest (Conservation) Act for diversion of forest land for non-forest infrastructure and development purposes, governed by the Ministry of Environment, Forest and Climate Change (MoEFCC) and state forest departments.

The application was submitted on 2026-09-07. The land requirement comprises 228.36 ha of forest land and 54.61 ha of non-forest land. Full proposal documents, boundary (KML) data, and the exact project location, where published by PARIVESH, are linked on this page. This record is updated as the clearance moves through verification, appraisal, and the final grant or rejection stage.

PARIVESH data

Proposal record

11 fields
Proposal Number
FP/BR/HYD/IRRIG/591169/2026
Organisation
SUn Hydro Energy Private LIMITED
Applicant
Amol Suryabhan Chikte
Clearance Type
Forest Clearance
Proposal Type
FC
Current Status
Pending at UA due to EDS by MS after PSC-I
Submission Date
2026-09-07
Nodal Accepted Date
07-SEP-2026
Shape of Project
Hybrid
Forest Land
228.36 Ha
Non-Forest Land
54.61 Ha

Where

Project location

3 fields
District
Nawada
State
Bihar
Total Land Area
282.97 Ha

Source files

Documents & boundary data

3 files

Data from the Government of India's PARIVESH environmental clearance portal.

Questions

Frequently asked questions

1What is the Environmental Clearance status of "1200 MW Gosaintari Pumped Storage Project"?

As per the latest PARIVESH data, proposal FP/BR/HYD/IRRIG/591169/2026 carries the status "Pending at UA due to EDS by MS after PSC-I". It is a infrastructure-sector project in Nawada, Bihar.

2Who is the applicant for this Environmental Clearance proposal?

The proposal was filed by Amol Suryabhan Chikte on behalf of SUn Hydro Energy Private LIMITED. The clearance type is Forest Clearance and it is tracked under PARIVESH reference FP/BR/HYD/IRRIG/591169/2026.

3What is the project cost and land requirement?

The proposal reports an estimated cost of ₹6,198 Cr and requires 282.97 Ha of land (228.36 ha forest, 54.61 ha non-forest).

4What is Environmental Clearance (EC) and why does this project need it?

Environmental Clearance is a mandatory approval under India's Environment Impact Assessment (EIA) framework, granted by the MoEFCC or the State Environment Impact Assessment Authority (SEIAA) via the PARIVESH portal. Projects that can significantly affect the environment must obtain EC — covering appraisal of pollution, land use, and ecological impact — before construction or expansion can lawfully begin.