Construction & Re-setting/Re-arrainging of new Pontoon Bridge, its maintainance and storing the Pontoon set at safe place on the side of River Koshi embankment at Kapsiya Ghat under in the District of Madhepura. (42 Sets)

Saharsa·Saharsa·Bihar

Admin Approval

₹2514 L

Agreement Amount

₹22,54,680.00 Cr

Commencement

05 Aug 2025

Scheduled Completion

04 Nov 2025

Project Details

DivisionSaharsa
DistrictSaharsa
SchemeNon-Plan
AA Vide No.466 (S)
AA Date21 Jan 2025
Bridge Type/LengthN/A

Cost & Timeline

Admin. Approval₹2513.99 lakh
Agreement Amount₹22,54,680.00 Cr
Commencement05 Aug 2025
Scheduled04 Nov 2025
RevisedN/A
Schedule StatusOn schedule

Construction & Re-setting/Re-arrainging of new Pontoon Bridge, its maintainance and storing the Pontoon set at safe place on the side of River Koshi embankment at Kapsiya Ghat under in the District of Madhepura. (42 Sets) is a bridge construction project in Saharsa district under the Bihar Rajya Pul Nirman Nigam Limited (BRPNNL), Saharsa. The agreement amount is ₹2254680.00 Cr, and the project is currently Unknown.

BRPNNL bridges improve rural and inter-district connectivity across Bihar. Other bridge projects in Saharsa district are listed below.

?

Frequently Asked Questions

QWhat is the current status of "Construction & Re-setting/Re-arrainging of new Pontoon Bridge, its maintainance "?
Status: Unknown. Physical achievement: N/A. On schedule. Scheduled completion: 04 Nov 2025. This is a BRPNNL bridge and road project in Saharsa, Bihar.
QWhat is the cost of this BRPNNL project?
The agreement amount for this project is ₹22,54,680.00 Cr. Administrative approval: ₹2513.99 lakh. The project is in Saharsa division, Saharsa district.
QWhich division is this BRPNNL project in?
This project is under BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) Saharsa division in Saharsa district, Bihar. Scheme: Non-Plan. AA Vide No.: 466 (S).
QWhat does BRPNNL do in Bihar?
BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) is a Bihar government corporation responsible for bridge and road construction across rural and semi-urban Bihar. "Construction & Re-setting/Re-arrainging of new Pontoon Bridg" in Saharsa is one of many bridge projects tracked through the Monthly Progress Report (MPR) system monitored on BiharInfraTales.