Saran Works·Gopalganj·Bihar
Admin Approval
₹86 L
Agreement Amount
—
Commencement
01 May 2008
Scheduled Completion
—
Bridge is located on the rural road. L.A Proposal under new L.A act has been submitted vide this office letter no. 171 (We) dated-10-04-2017. Toal 2 dismil land required to acquire from only one raiyat. Bridge work is completed along with one side of approach road. decision for land acquisition under perpetual lease may be taken.