Gaya Ji·Gaya Jee·Bihar
Admin Approval
₹9017 L
Agreement Amount
₹67.79 Cr
Commencement
26 Dec 2025
Scheduled Completion
25 Dec 2027
● Site Mobilized. ● Total 84 nos. of building & shops in alignment of ROB. ● Route diversion plan has been prepared by SDM, Sadar, Gaya. ● GAD Approved by ECR, Hajipur dated 11.03.2026 Remarks for LA: ● LA-65% & Area 2.0431 Acre ● Mauza-Bairagi, Pahsi & Total Raiyat-115 Nos. ● Expert Committee done on 16.09.25 & Section-11(i) published on dt. 07.02.26. ● Public hearing for objection raised against publication of Section-11(i) held on 08.04.26