BuxarBRPNNLUnknown

Construction of ROB Approach in between Buxar & Baruna Railway Station in lieu of LC No.-70B under Buxar District

Ara·Buxar·Bihar

Admin Approval

₹3534 L

Agreement Amount

₹26,40,400.00 Cr

Commencement

25 Oct 2022

Scheduled Completion

24 Jan 2024

Project Details

DivisionAra
DistrictBuxar
SchemePlan
AA Vide No.Letter No-209(S)
AA Date24 Jan 2022
Bridge Type/LengthN/A

Cost & Timeline

Admin. Approval₹3533.75 lakh
Agreement Amount₹26,40,400.00 Cr
Commencement25 Oct 2022
Scheduled24 Jan 2024
Revised30 Jun 2026
Schedule StatusOn schedule

Construction of ROB Approach in between Buxar & Baruna Railway Station in lieu of LC No.-70B under Buxar District is a bridge construction project in Buxar district under the Bihar Rajya Pul Nirman Nigam Limited (BRPNNL), Ara. The agreement amount is ₹2640400.00 Cr, and the project is currently Unknown.

BRPNNL bridges improve rural and inter-district connectivity across Bihar. Other bridge projects in Buxar district are listed below.

Remarks

Retrofitting work near expansion joint is under progress.

?

Frequently Asked Questions

QWhat is the current status of "Construction of ROB Approach in between Buxar & Baruna Railway Station in lieu o"?
Status: Unknown. Physical achievement: N/A. On schedule. Scheduled completion: 24 Jan 2024. Revised date: 30 Jun 2026. This is a BRPNNL bridge and road project in Buxar, Bihar.
QWhat is the cost of this BRPNNL project?
The agreement amount for this project is ₹26,40,400.00 Cr. Administrative approval: ₹3533.75 lakh. The project is in Ara division, Buxar district.
QWhich division is this BRPNNL project in?
This project is under BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) Ara division in Buxar district, Bihar. Scheme: Plan. AA Vide No.: Letter No-209(S).
QWhat does BRPNNL do in Bihar?
BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) is a Bihar government corporation responsible for bridge and road construction across rural and semi-urban Bihar. "Construction of ROB Approach in between Buxar & Baruna Railw" in Buxar is one of many bridge projects tracked through the Monthly Progress Report (MPR) system monitored on BiharInfraTales.