KatiharBRPNNLUnknown

Construction of ROB and approach road in lieu of LC No- KM-1 (km-0/7-8) (Katihar-Mukuriya) Santoshi Chowk & LC No- KJ-1 (km-0/8-9) (Katihar-Jogbani) Sahebpara Chowk in Katihar District.

Katihar·Katihar·Bihar

Admin Approval

₹19365 L

Agreement Amount

₹96.19 Cr

Commencement

22 Sep 2025

Scheduled Completion

21 Sep 2028

Project Details

DivisionKatihar
DistrictKatihar
SchemeROB
AA Vide No.905(s)
AA Date05 Feb 2025
Bridge Type/LengthN/A

Cost & Timeline

Admin. Approval₹19365.06 lakh
Agreement Amount₹96.19 Cr
Commencement22 Sep 2025
Scheduled21 Sep 2028
Revised21 Sep 2028
Schedule StatusOn schedule

Construction of ROB and approach road in lieu of LC No- KM-1 (km-0/7-8) (Katihar-Mukuriya) Santoshi Chowk & LC No- KJ-1 (km-0/8-9) (Katihar-Jogbani) Sahebpara Chowk in Katihar District. is a bridge construction project in Katihar district under the Bihar Rajya Pul Nirman Nigam Limited (BRPNNL), Katihar. The agreement amount is ₹96.19 Cr, and the project is currently Unknown.

BRPNNL bridges improve rural and inter-district connectivity across Bihar. Other bridge projects in Katihar district are listed below.

Remarks

Civil, Water Pipe line shifting, Electrical Utility Shifting & Railway Quarter shifting etc. work in progress.

?

Frequently Asked Questions

QWhat is the current status of "Construction of ROB and approach road in lieu of LC No- KM-1 (km-0/7-8) (Katihar"?
Status: Unknown. Physical achievement: N/A. On schedule. Scheduled completion: 21 Sep 2028. Revised date: 21 Sep 2028. This is a BRPNNL bridge and road project in Katihar, Bihar.
QWhat is the cost of this BRPNNL project?
The agreement amount for this project is ₹96.19 Cr. Administrative approval: ₹19365.06 lakh. The project is in Katihar division, Katihar district.
QWhich division is this BRPNNL project in?
This project is under BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) Katihar division in Katihar district, Bihar. Scheme: ROB. AA Vide No.: 905(s).
QWhat does BRPNNL do in Bihar?
BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) is a Bihar government corporation responsible for bridge and road construction across rural and semi-urban Bihar. "Construction of ROB and approach road in lieu of LC No- KM-1" in Katihar is one of many bridge projects tracked through the Monthly Progress Report (MPR) system monitored on BiharInfraTales.