ArariaBRPNNLUnknown
Construction of ROB and approach road in lieu of Level Crossing No.-65 Railway line Km-96/1 to 96/2 Between Railway Station Forbesganj-Bathnaha on NH-57A at Subash Chowk in Araria District.
Katihar·Araria·Bihar
Admin Approval
₹11565 L
Agreement Amount
₹73.40 Cr
Commencement
12 Jun 2025
Scheduled Completion
11 Jun 2028
Project Details
DivisionKatihar
DistrictAraria
SchemeROB
AA Vide No.914(s)
AA Date05 Feb 2025
Bridge Type/LengthN/A
Cost & Timeline
Admin. Approval₹11564.55 lakh
Agreement Amount₹73.40 Cr
Commencement12 Jun 2025
Scheduled11 Jun 2028
Revised11 Nov 2028
Schedule StatusOn schedule
Construction of ROB and approach road in lieu of Level Crossing No.-65 Railway line Km-96/1 to 96/2 Between Railway Station Forbesganj-Bathnaha on NH-57A at Subash Chowk in Araria District. is a bridge construction project in Araria district under the Bihar Rajya Pul Nirman Nigam Limited (BRPNNL), Katihar. The agreement amount is ₹73.40 Cr, and the project is currently Unknown.
BRPNNL bridges improve rural and inter-district connectivity across Bihar. Other bridge projects in Araria district are listed below.
Remarks
Work is in progress. (Pragati Yatra Project)
?
Frequently Asked Questions
- QWhat is the current status of "Construction of ROB and approach road in lieu of Level Crossing No.-65 Railway l"?
- Status: Unknown. Physical achievement: N/A. On schedule. Scheduled completion: 11 Jun 2028. Revised date: 11 Nov 2028. This is a BRPNNL bridge and road project in Araria, Bihar.
- QWhat is the cost of this BRPNNL project?
- The agreement amount for this project is ₹73.40 Cr. Administrative approval: ₹11564.55 lakh. The project is in Katihar division, Araria district.
- QWhich division is this BRPNNL project in?
- This project is under BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) Katihar division in Araria district, Bihar. Scheme: ROB. AA Vide No.: 914(s).
- QWhat does BRPNNL do in Bihar?
- BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) is a Bihar government corporation responsible for bridge and road construction across rural and semi-urban Bihar. "Construction of ROB and approach road in lieu of Level Cross" in Araria is one of many bridge projects tracked through the Monthly Progress Report (MPR) system monitored on BiharInfraTales.