Darbhanga·Madhubani·Bihar
Admin Approval
₹17800 L
Agreement Amount
₹9244091.80 Cr
Commencement
20 Aug 2025
Scheduled Completion
19 Feb 2028
1) Piling work in progress a) Foundation (Pile)-50/209 Nos b) Pile cap-4/33 Nos. c) Pier shaft-2/37 Nos. d) Pier cap-0/31 Nos. e) Girder-4/88 Nos. f) Deck slab-0/29 Nos. g) Steel girder-0/10 Nos. h) Steel Bow Section-0/01 Nos.