Saran Works·Gopalganj·Bihar
Admin Approval
₹77 L
Agreement Amount
—
Commencement
—
Scheduled Completion
—
Bridge is located on the rural Road. Bridge work complete along with approch road. Traffic started. Total 11 Dismil Land required to acquire from only one raiyat in the proposal. DM Gopalganj returned LA porposal to acquire under perpetual lease vide Letter No.-342 dated 03-05-2018. Dy Chief Engineer, North Bihar Circle B.R.P.N.N.L Patna, directed vide Letter No. 549 (We) dt. 02-06-2018. that DM is the competent authority for acquire the above land under perpetual lease.