NawadaBRPNNLUnknown

Construction of Nawada Bypass from 97th Km of NH-31 to Kadirganj SH-08 (Near approach of Sakri River Bridge) along with ROB near Sadipur Halt in the district of Nawada.

Nalanda·Nawada·Bihar

Admin Approval

₹18162 L

Agreement Amount

₹107.27 Cr

Commencement

06 Oct 2025

Scheduled Completion

05 Oct 2027

Project Details

DivisionNalanda
DistrictNawada
SchemeState Plan
AA Vide No.1712 (S)
AA Date28 Feb 2025
Bridge Type/LengthN/A

Cost & Timeline

Admin. Approval₹18162.21 lakh
Agreement Amount₹107.27 Cr
Commencement06 Oct 2025
Scheduled05 Oct 2027
RevisedN/A
Schedule StatusOn schedule

Construction of Nawada Bypass from 97th Km of NH-31 to Kadirganj SH-08 (Near approach of Sakri River Bridge) along with ROB near Sadipur Halt in the district of Nawada. is a bridge construction project in Nawada district under the Bihar Rajya Pul Nirman Nigam Limited (BRPNNL), Nalanda. The agreement amount is ₹107.27 Cr, and the project is currently Unknown.

BRPNNL bridges improve rural and inter-district connectivity across Bihar. Other bridge projects in Nawada district are listed below.

Remarks

1.)Site Camp Completed. LA Status - 2.) 75.75 Acre Land to be Acquired. For Land Acquisition Section 11 (1) Completed. Section 19 (1) is in Progress. 3.) Demarcation of Acquisition Land is in Progress.

?

Frequently Asked Questions

QWhat is the current status of "Construction of Nawada Bypass from 97th Km of NH-31 to Kadirganj SH-08 (Near app"?
Status: Unknown. Physical achievement: N/A. On schedule. Scheduled completion: 05 Oct 2027. This is a BRPNNL bridge and road project in Nawada, Bihar.
QWhat is the cost of this BRPNNL project?
The agreement amount for this project is ₹107.27 Cr. Administrative approval: ₹18162.21 lakh. The project is in Nalanda division, Nawada district.
QWhich division is this BRPNNL project in?
This project is under BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) Nalanda division in Nawada district, Bihar. Scheme: State Plan. AA Vide No.: 1712 (S).
QWhat does BRPNNL do in Bihar?
BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) is a Bihar government corporation responsible for bridge and road construction across rural and semi-urban Bihar. "Construction of Nawada Bypass from 97th Km of NH-31 to Kadir" in Nawada is one of many bridge projects tracked through the Monthly Progress Report (MPR) system monitored on BiharInfraTales.