Ara·Rohtas·Bihar
Admin Approval
₹21013 L
Agreement Amount
₹13647000.00 Cr
Commencement
03 Oct 2025
Scheduled Completion
02 Apr 2028
Previous Contractor terminated after cracks in pier & Previous Expenditure is Rs. 5504 Lakhs. Balance work currenct Cumulative expenditure Rs. 545.00 Lakhs. Balance Work Physical progress:- Foundation-50% Sub Structure- 5% Super Structure -0.00% Approach- 0.00%