Central Government TenderExpired

Construction of Pre Engineered Building (PEB) including Foundation, Civil Works complete with Finishing for New Passenger Terminal Building at Nischintapur Yard in connection with Agartala Akhaura New Rail Link Project

Issued by: Ircon International Limited
Location: Agartala, Tripura
Central Government Tender○ Closed
Ref. NoIRCON/2056/AANRLP/Tender/ PEB and FOUNDATION/2024 25
Est. Value₹28.84 Cr
Deadline07-Apr-2025 03:00 PM
TypeOpen Tender
Agartala, Tripura
Published 21-Mar-2025 06:30 PM

Tender Specifications & Timeline

13 Fields
Estimated Value
₹28.84 Cr
Organisation
Ircon International Limited
Reference No.
IRCON/2056/AANRLP/Tender/ PEB and FOUNDATION/2024 25
Status
Expired
Location
Agartala, Tripura
Source
Central Govt. Portal
Status Stage
AOC
Published Date
21-Mar-2025 06:30 PM
Submission Deadline
07-Apr-2025 03:00 PM
Submission Start
27-Mar-2025 03:00 PM
Bid Opening Date
08-Apr-2025 03:00 PM
Bid Opening Place
Agartala
Period of Work
180 Days

Award of Contract (AOC) Details

Awardee / Contractor

TRIBENI CONSTRUCTIONS LIMITED

Award Date: 20-May-2025

Completion Period: 180 Days

Contract Financials & Scope

INR 285,214,542.71

Work awarded for Construction of Pre Engineered Building (PEB) including Foundation and Civil Works

Contract Award Info Updated 20-May-2025 11:19 AM by Pratyush Kumar Sahu

L1 Bidder & Competitor IntelligenceAOC Intel

Total Bidders

3

Winning Bid (L1)

₹28.52 Cr

Estimated Value (PAC)

₹28.84 Cr

Margin vs Estimate

-1.10%

Winning Contractor (L1 - Official Awardee)

Accepted-AOC

L1 to L2 Spread

+11.19%

Completion Period

180 days

AOC Award Date

20-May-2025

RankBidder / ContractorQuoted BidGap vs L1vs EstimateStatus
L1₹28.52 Cr0.0% (L1)-1.10%Accepted-AOC
L2₹31.71 Cr+11.19%Rejected-FinRejected-Finance
L3₹36.19 Cr+26.90%Rejected-FinRejected-Finance

This railways tender covers construction of Pre Engineered Building (PEB) including Foundation, Civil Works complete with Finishing for New Passenger Terminal Building at Nischintapur Yard in connection with Agartala Akhaura New Rail Link Project, issued by Ircon International Limited under reference IRCON/2056/AANRLP/Tender/ PEB and FOUNDATION/2024 25. The estimated contract value is ₹28.84 Cr, and the tender is currently Expired. Following contract finalisation, the work was awarded to TRIBENI CONSTRUCTIONS LIMITED for a total value of ₹28.52 Cr.

This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Agartala, Tripura. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.

Tender Documents

Download official tender documents, technical specifications, schedules, and BOQ files

4 Files Available
BOQ COMPARATIVE CHART

BOQ Comparative Chart

Download Document
PDF

techsummary_260237.pdf

Download Document
PDF

finsummary_260237.pdf

Download Document
PDF

TRIBENILOA.pdf

Download Document
Submitted Bids & Bidder Details
Allied Infrastructures And Projects Private Limited
#838274
Rejected-Finance
Submitted: 07-Apr-2026 10:23 PM
Fin. Value: 36,19,25,430.84
Rank: L3
Updated: 20-May-2025 11:09 AM

Being L3 Bidder

JHAJHARIA NIRMAN LTD
#837094
Rejected-Finance
Submitted: 07-Apr-2025 12:57 PM
Fin. Value: 31,71,38,961.19
Rank: L2
Updated: 20-May-2025 11:09 AM

Being L2 Bidder

TRIBENI CONSTRUCTIONS LIMITED
#838349
Accepted-AOC
Submitted: 05-Apr-2025 06:37 PM
Fin. Value: 28,52,14,542.71
Rank: L1
Updated: 20-May-2025 11:19 AM

L1 Bidder qualifying Techno-financial Bid for award of work

Bid Evaluation Details & Logs

technical evaluation

technical evaluation

Date: 20-May-2025 10:56 AM

Officer: Pratyush Kumar Sahu

finance evaluation

finance evaluation

Date: 20-May-2025 11:09 AM

Officer: Pratyush Kumar Sahu

About This Procurement Notice

This central government tender was issued by Ircon International Limited. The estimated contract value is ₹28.84 Cr. Bids must be submitted by 07-Apr-2025 03:00 PM.

BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.

?

Frequently Asked Questions

QWhat is the status of the tender "Construction of Pre Engineered Building (PEB) including Foundation, Civil Works "?
The current status of this tender is "Expired". The submission deadline is 07-Apr-2025 03:00 PM. This information is sourced from official government procurement portals.
QWho issued this central government tender?
This tender was issued by Ircon International Limited. The reference number is IRCON/2056/AANRLP/Tender/ PEB and FOUNDATION/2024 25. It is a central government procurement notice.
QWhat is the estimated value of this tender?
The estimated tender value is ₹28.84 Cr. This is the approximate contract value as disclosed in the official tender document.
QWho won the contract for this tender?
The contract for "Construction of Pre Engineered Building (PEB) including Foundation, Civil Works complete with Finishing for New Passenger Terminal Building at Nischintapur Yard in connection with Agartala Akhaura New Rail Link Project" was awarded to TRIBENI CONSTRUCTIONS LIMITED with an awarded contract value of ₹28.52 Cr.
QWhat is the final awarded contract value?