Construction of Compound wall, Perimeter Road, RCC Drain for NITB at Trichy Airport, Trichy
Tender Details
Financial & Timeline
Award of Contract (AOC) Details
Awardee / Contractor
Garg Associates
Award Date: 06-May-2023
Completion Period: 180 Days
Contract Financials & Scope
INR 45,350,380
Contract Award Info Updated 27-Mar-2024 12:42 PM by NARASIMHA RAO K
This airports tender covers construction of Compound wall, Perimeter Road, RCC Drain for NITB at Trichy Airport, Trichy, issued by Airports Authority of India under reference AAI/TRY/PROJ/NITB C.WALL/22-23/. The estimated contract value is ₹5.34 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Tiruchirappalli International Airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents & Downloads
techsummary_162470.pdf
Key: 2023_AAI_148536_1/techsummary_162470.pdf
BOQ Comparative Chart
Key: 2023_AAI_148536_1/BOQ Comparative Chart.xlsx
finsummary_162470.pdf
Key: 2023_AAI_148536_1/finsummary_162470.pdf
AwardLetter-CompoundWall.pdf
Key: 2023_AAI_148536_1/AwardLetter-CompoundWall.pdf
Submitted Bids & Bidder Details
L2
L1 Bidder
L7
L4
L5
L3
L6
| Bid No. / Bidder | Submitted On | Status | Fin. Value | Fin. Rank | Remarks / Logs |
|---|---|---|---|---|---|
CREATORS ENGINEERS AND INTERIORS PVT LTD #540556 | 29-Mar-2023 05:32 PM | Rejected-Finance Updated: 03-May-2023 06:58 PM | 4,56,34,939.00 | LL2 | L2 |
Garg Associates #539703 | 28-Mar-2023 11:24 PM | Accepted-AOC Updated: 27-Mar-2024 12:42 PM | 4,53,50,380.00 | LL1 | L1 Bidder |
H S OBEROI BUILDTECH PVT LTD #538841 | 29-Mar-2023 12:31 PM | Rejected-Finance Updated: 03-May-2023 06:58 PM | 5,99,15,570.00 | LL7 | L7 |
Intex Space Solutions Private Limited #540497 | 29-Mar-2023 05:17 PM | Rejected-Finance Updated: 03-May-2023 06:58 PM | 4,93,14,600.00 | LL4 | L4 |
M/S SRI MARUTHI CONSTRUCTIONS #539196 | 29-Mar-2023 01:55 PM | Rejected-Finance Updated: 03-May-2023 06:58 PM | 4,99,84,780.00 | LL5 | L5 |
M/s.Thomas iyadurai Infrastructure Pvt Ltd #539241 | 29-Mar-2023 02:57 PM | Rejected-Finance Updated: 03-May-2023 06:58 PM | 4,76,48,278.49 | LL3 | L3 |
VISHAL INFRASTRUCTURE LTD #535407 | 27-Mar-2023 03:14 PM | Rejected-Finance Updated: 03-May-2023 06:58 PM | 5,16,02,647.00 | LL6 | L6 |
Bid Evaluation Details & Logs
technical bid opening
Date: 05-Apr-2023 11:45 AM
Officer: NARASIMHA RAO K
Technical Bid was opened on 30-03-2023 at 18.00 Hrs
technical evaluation
Date: 13-Apr-2023 12:05 PM
Officer: NARASIMHA RAO K
finance bid opening
Date: 03-May-2023 06:39 PM
Officer: NARASIMHA RAO K
Financial bid opened
finance evaluation
Date: 03-May-2023 06:58 PM
Officer: NARASIMHA RAO K
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹5.34 Cr. Bids must be submitted by 29-Mar-2023 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- What is the status of the tender "Construction of Compound wall, Perimeter Road, RCC Drain for NITB at Trichy Airp"?
- The current status of this tender is "Expired". The submission deadline is 29-Mar-2023 06:00 PM. This information is sourced from official government procurement portals.
- Who issued this Bihar government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/TRY/PROJ/NITB C.WALL/22-23/. It is a central government procurement notice.
- What is the estimated value of this tender?
- The estimated tender value is ₹5.34 Cr. This is the approximate contract value as disclosed in the official tender document.