| Project No. | 865 |
| Wing | South Wing |
| Division | Road Division Patna City. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹203.36 Cr |
| Sanctioned Length | 45.70 km |
| Contractor | Surendra Prasad & Lahri Construction Pvt. Ltd |
| AA Date | 05-03-2025 |
| Start Date | 04-10-2025 |
| Expected Completion | 31-12-2027 |
work in progress. 10 nos. RCC Box culvert & 01 HP culvert completed & 06 nos. is in progress. Utility Shifting Estimate received and work in progress. NOC granted vide DFO Patna lt. no. 3558 dt. 31.12.25. Tree Cutting work in progress.
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Patna City.
Visited: 24 Feb 2026"Road inspection was carried out on 24/02/2026. During inspection, the condition of the road and ongoing works were reviewed, and necessary observations/instructions were communicated to the Executive Engineer and Contractor."