| Project No. | 848 |
| Wing | North Wing |
| Division | Road Division Muzaffarpur -1 |
| Circle | North Bihar Road Circle Muzaffarpur |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹69.02 Cr |
| Sanctioned Length | 7.65 km |
| Contractor | M/s Adarsh Construction |
| AA Date | 17-03-2025 |
| Start Date | 28-07-2025 |
| Expected Completion | 27-01-2027 |
Work in Progress Proposal for falling & Translocation of trees have been submitted to "Parivesh Portal" on dated 17.12.2025. Work stop vide DFO Letter No. 204 dt. 24.01.2026 .NFL land demanded to DM muzaffarpur vide letter no 363 dt 10.02.2026. NFL land make available vide DM muzaffarpur letter no 3131 dt 20.04.2026. Ora postal resubmitted in parivesh portal on 2/6/2026
Superintending Engineer quality visit record
North Bihar Road Circle Muzaffarpur · Road Division Muzaffarpur -1
Visited: 21 Sept 2025"Work is in progress, Instructed to keep progress according to work program"