| Project No. | 822 |
| Wing | South Wing |
| Division | Road Division Patna City. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹5.69 Cr |
| Sanctioned Length | 1.30 km |
| Contractor | Bansidhar Construction Pvt. Ltd. |
| AA Date | 23-09-2024 |
| Start Date | 22-12-2025 |
| Expected Completion | 31-10-2026 |
Work order issued on 22.12.25. Agreement done on 28.01.26.Clearing & Grubbing and Drain work in progress.Revised Estimate sanctioned vide CE(S) lt. no. 1428we dt.04.05.26.
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Patna City.
Visited: 7 May 2026"Road inspection was carried out on 07/05/2026. During inspection, ongoing works were reviewed, and necessary observations/instructions were communicated to the concerned officials/agency"