MDRRCD BiharCompleted

IRQP work of NH Khirma-Jalwara-Asraha-Bishfi Road

#82
Road Division Darbhanga.
Road Circle Darbhanga.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹8.69 Cr
Length10.50 km
Start27-07-2020
Completion15-03-2023
MDR · North Wing
Road Division Darbhanga.
Vidhyarthi Construction Pvt. Ltd.

Project Details

6 Fields
Project No.
82
Wing
North Wing
Division
Road Division Darbhanga.
Circle
Road Circle Darbhanga.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹8.69 Cr
Sanctioned Length
10.50 km
Contractor
Vidhyarthi Construction Pvt. Ltd.
AA Date
19-09-2019
Start Date
27-07-2020
Expected Completion
15-03-2023

IRQP work of NH Khirma-Jalwara-Asraha-Bishfi Road is a Bihar Road Construction Department (RCD) project under Road Division Darbhanga., classified as a MDR. The agreement amount for this project is ₹8.69 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Completed

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "IRQP work of NH Khirma-Jalwara-Asraha-Bishfi Road"?
Status: Completed. This MDR project under Road Division Darbhanga. (Road Circle Darbhanga.) covers 10.50 km of road work. Expected completion: 15-03-2023.
QWho is the contractor for RCD project 82?
The contractor for this project is Vidhyarthi Construction Pvt. Ltd.. Project number: 82. Division: Road Division Darbhanga.. Administrative approval date: 19-09-2019.
QWhat is the agreement value for this Bihar road project?
The agreement value for "IRQP work of NH Khirma-Jalwara-Asraha-Bishfi Road" is ₹8.69 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Darbhanga..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 82 "IRQP work of NH Khirma-Jalwara-Asraha-Bishfi Road" is one of thousands of road improvement and construction works tracked by BiharInfraTales.