W/S work of Darbhanga Tower to Bhagat Singh Chowk, Pansari Petrol Pump to Mirzapur chowk, Darbhanga Tower to Raja Babu Petrol Pump, Hasan Chowk, Lalbagh Post Office, PWD Road NCC to Bhogendra Jha Chowk PWD Milan Point, Lalbagh Post office to Pansari Petr
Project Details
6 FieldsCost & Timeline
6 FieldsW/S work of Darbhanga Tower to Bhagat Singh Chowk, Pansari Petrol Pump to Mirzapur chowk, Darbhanga Tower to Raja Babu Petrol Pump, Hasan Chowk, Lalbagh Post Office, PWD Road NCC to Bhogendra Jha Chowk PWD Milan Point, Lalbagh Post office to Pansari Petr is a Bihar Road Construction Department (RCD) project under Road Division Darbhanga., classified as a MDR. The agreement amount for this project is ₹13.72 Cr, and the current status is Ongoning.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work suspended by the order of Hon'ble High Court, Patna on dt. 01.11.2025 in CWJC No. 13936/2025. Case Disposed off Dt 28.07.2026 by Honble High Court Patna and This matter transferred to D.M. Darbhanga for further necessary action. Information send vide this office letter no. 2253 dt. 11.08.2026 to D.M. Darbhanga.
SE Inspection Log
Superintending Engineer quality visit record
Road Circle Darbhanga. · Road Division Darbhanga.
Visited: 5 Sept 2024"इस सड़क की कुल लंबाई 2.70 किलोमीटर है। इस कार्य के संवेदक महेश कुमार सिंह हैं। इस कार्य के प्रारम्भ की तिथि 16.03.2024 एवं समाप्ति की तिथि 15.01.2025 है। पथ के निरिक्षण के क्रम में ड्रेन का कार्य प्रगति में पाया गया। PQC का कार्य प्रारम्भ नहीं पाया गया। भोगेन्द्र झा चौक के नजदीक बन रहे बड़े नाले में प्रोटेक्शन के साथ कार्य करने का निदेश दिया गया ताकि नाला के बगल में अवस्थित मकान /चहारदीवारी को क्षति नहीं पहुंचे। बाजार भाग में बन रहे नाला को PQC सरफेस के निचे रखने का निदेश दिया गया , साथ ही बगल के Plinth से नीचे रखने का निदेश दिया गया। कुल पथ के अंश में एक्सिस्टिंग PQC का सरफेस अच्छा पाया गय। उन पथ के अंशो में PQC कार्य नहीं करने एवं चौड़ीकरण एवं ड्रेन का कार्य करने का निदेश दिया गया। कंक्रीट की गुणवत्ता सुनिश्चित करने का निदेश कार्यपालक अभियंता को दिया गया। *Inspection Report PDF is Attached. Refer to serial no 2 of attached file"
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "W/S work of Darbhanga Tower to Bhagat Singh Chowk, Pansari Petrol Pump to Mirzap"?
- Status: Ongoning. This MDR project under Road Division Darbhanga. (Road Circle Darbhanga.) covers 2.70 km of road work. Expected completion: 15-01-2025.
- QWho is the contractor for RCD project 669?
- The contractor for this project is MAHESH KUMAR SINGH. Project number: 669. Division: Road Division Darbhanga.. Administrative approval date: 21-09-2023.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "W/S work of Darbhanga Tower to Bhagat Singh Chowk, Pansari P" is ₹13.72 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Darbhanga..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 669 "W/S work of Darbhanga Tower to Bhagat Singh Chowk, Pansari P" is one of thousands of road improvement and construction works tracked by BiharInfraTales.