| Project No. | 624 |
| Wing | South Wing |
| Division | Road Division Jehanabad. |
| Circle | Magadh Road Circle Gaya |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹84.26 Cr |
| Sanctioned Length | 7.48 km |
| Contractor | BABA HANS CONST. PVT. LTD. |
| AA Date | 30-09-2022 |
| Start Date | 06-04-2023 |
| Expected Completion | 31-12-2026 |
Widening work Stopped due to forest clearance Issue. Stage-1 Clearance is pending. Total 8.705 Hect of Jila Parishad Raiyati Land involved in widening of road for which valuation amount is 302.40 Cr. Valuation of Jila Parishad & Nagar Parishad shop in alignment of road is 83.64 lakh. In VC under chairmanship of Chief Sec. Bihar dated 26.05.2026, it is directed that Road work has to be carried out on the existing alignment and no widening work is to be undertaken. In that case, forest clearance & NOC from Jila parishad not required.
Superintending Engineer quality visit record
Magadh Road Circle Gaya · Road Division Jehanabad.
Visited: 5 Mar 2025"Attached Report"