MDRRCD BiharCompleted

Widening and Strengthening work (from single lane to intermediate lane) of Dhansoi-Dinara Road (From Km 0.00 to Km 13.60) including Road crust Work, Bituminous Work, Cross Drain, Utility Shifting Work, Road Safety Audit work under Road Division, Buxar for

#58
Road Division Buxar.
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹22.13 Cr
Length13.60 km
Start04-05-2020
Completion03-09-2021
MDR · South Wing
Road Division Buxar.
Memraj Const Pvt. Ltd.

Project Details

6 Fields
Project No.
58
Wing
South Wing
Division
Road Division Buxar.
Circle
Bhojpur Road Circle Arrah.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹22.13 Cr
Sanctioned Length
13.60 km
Contractor
Memraj Const Pvt. Ltd.
AA Date
16-08-2019
Start Date
04-05-2020
Expected Completion
03-09-2021

Widening and Strengthening work (from single lane to intermediate lane) of Dhansoi-Dinara Road (From Km 0.00 to Km 13.60) including Road crust Work, Bituminous Work, Cross Drain, Utility Shifting Work, Road Safety Audit work under Road Division, Buxar for is a Bihar Road Construction Department (RCD) project under Road Division Buxar., classified as a MDR. The agreement amount for this project is ₹22.13 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Road Work Completed. Road Furniture & other works in progress.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Widening and Strengthening work (from single lane to intermediate lane) of Dhans"?
Status: Completed. This MDR project under Road Division Buxar. (Bhojpur Road Circle Arrah.) covers 13.60 km of road work. Expected completion: 03-09-2021.
QWho is the contractor for RCD project 58?
The contractor for this project is Memraj Const Pvt. Ltd.. Project number: 58. Division: Road Division Buxar.. Administrative approval date: 16-08-2019.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Widening and Strengthening work (from single lane to interme" is ₹22.13 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Buxar..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 58 "Widening and Strengthening work (from single lane to interme" is one of thousands of road improvement and construction works tracked by BiharInfraTales.