Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /RCD PMIS
  3. /Construction of 2 lane Dhansoi Byepass Road under
MDRRCD BiharTender

Construction of 2 lane Dhansoi Byepass Road under Road Division Buxar

#896
Road Division Buxar.
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road Project◐ Tender
AgreementN/A
Length4.05 km
StartN/A
Completion09-01-2026
MDR · South Wing
Road Division Buxar.

Project Details

Project No.896
WingSouth Wing
DivisionRoad Division Buxar.
CircleBhojpur Road Circle Arrah.
Road TypeMDR
HeadSulabh Samparkata

Cost & Timeline

Agreement ValueN/A
Sanctioned Length4.05 km
ContractorN/A
AA DateN/A
Start DateN/A
Expected Completion09-01-2026

Remarks

Green Field Project. Land Acquisition- 12.49 Ha. In process of Land Acquisition. Bhu-Arjan Adhiyachna submitted to DLAO, Buxar (Lt.-892 Dt.-14.05.2025). SIA process in progress. Technical Expert Committee report submitted to DLAO on 12.03.2026. Section 11 in process. Re-Tender invited on 09.12.2025 due to single bidder after technical evaluation. Technical Bid opened on 09.01.2026. Technical Bid Evaluation forwarded by SE Bhojpur on 13.01.2026. Objection resolution done by dept . Financial Bid opened on 16.04.2026. forwarded to SE Bhojpur vide Lt 689 dt 17.04.2026

Frequently Asked Questions

What is the current status of the Bihar RCD project "Construction of 2 lane Dhansoi Byepass Road under Road Division Buxar"?
Status: Tender. This MDR project under Road Division Buxar. (Bhojpur Road Circle Arrah.) covers 4.05 km of road work. Expected completion: 09-01-2026.
Who is the contractor for RCD project 896?
The contractor for this project is Not disclosed. Project number: 896. Division: Road Division Buxar.. Administrative approval date: N/A.
What is the agreement value for this Bihar road project?
Agreement cost details are not available in the current PMIS data for this project. Please refer to the official Bihar RCD PMIS records.
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 896 "Construction of 2 lane Dhansoi Byepass Road under Road Divis" is one of thousands of road improvement and construction works tracked by BiharInfraTales.
Bihar RCD PMIS Dashboard

Related Resources

RCD

Bihar RCD PMIS Dashboard

All RCD road projects across Bihar

Roads

Bihar Road Network GIS Map

Visual map of Bihar highway and road network

NHAI

NHAI Drone Tracker

National highway drone-monitored progress

BRPNNL

BRPNNL Bridge Projects

Bihar bridge project monitor

Projects

Bihar Infrastructure Projects

All government infrastructure project tracker

Tenders

Bihar Government Tenders

Active procurement notices for road projects

IPM

Central Project Monitor (IPM)

Centrally-funded infrastructure in Bihar

Cabinet

Bihar Cabinet Decisions

Government policy for infrastructure projects

EC

Stage-1 EC Clearances

Forest and environmental clearances

Districts

Bihar District Data

District-level infrastructure and demographics

  1. BiharInfraTales
  2. /RCD PMIS
  3. /Construction of 2 lane Dhansoi Byepass Road under