Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /RCD PMIS
  3. /Construction of Garkha Bypass
MDRRCD BiharOngoning

Construction of Garkha Bypass

#572
Road Division Sonepur
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹40.57 Cr
Length9.00 km
Start28-02-2024
Completion27-12-2026
MDR · North Wing
Road Division Sonepur
M/s Sunny Engineering Works

Project Details

Project No.572
WingNorth Wing
DivisionRoad Division Sonepur
CircleSaran Road Circle Hajipur.
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹40.57 Cr
Sanctioned Length9.00 km
ContractorM/s Sunny Engineering Works
AA Date30-09-2022
Start Date28-02-2024
Expected Completion27-12-2026

Remarks

(i) L/A in progress, L/A acquired 65.3063 acr. cost Rs. 3748.3776 lakh, Total Panchati -610, out of 610 only 95 panchati have been paid (ii) H.L bridge superstructure Completed. 11 nos. Box culvert completed 2 nos. in box culvert in progress, E/w in progress, work delay due to L.A issue. 1 nos. H.L Bridge superstructure in completed.

Frequently Asked Questions

What is the current status of the Bihar RCD project "Construction of Garkha Bypass"?
Status: Ongoning. This MDR project under Road Division Sonepur (Saran Road Circle Hajipur.) covers 9.00 km of road work. Expected completion: 27-12-2026.
Who is the contractor for RCD project 572?
The contractor for this project is M/s Sunny Engineering Works. Project number: 572. Division: Road Division Sonepur. Administrative approval date: 30-09-2022.
What is the agreement value for this Bihar road project?
The agreement value for "Construction of Garkha Bypass" is ₹40.57 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Sonepur.
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 572 "Construction of Garkha Bypass" is one of thousands of road improvement and construction works tracked by BiharInfraTales.
Bihar RCD PMIS Dashboard

Related Resources

RCD

Bihar RCD PMIS Dashboard

All RCD road projects across Bihar

Roads

Bihar Road Network GIS Map

Visual map of Bihar highway and road network

NHAI

NHAI Drone Tracker

National highway drone-monitored progress

BRPNNL

BRPNNL Bridge Projects

Bihar bridge project monitor

Projects

Bihar Infrastructure Projects

All government infrastructure project tracker

Tenders

Bihar Government Tenders

Active procurement notices for road projects

IPM

Central Project Monitor (IPM)

Centrally-funded infrastructure in Bihar

Cabinet

Bihar Cabinet Decisions

Government policy for infrastructure projects

EC

Stage-1 EC Clearances

Forest and environmental clearances

Districts

Bihar District Data

District-level infrastructure and demographics

  1. BiharInfraTales
  2. /RCD PMIS
  3. /Construction of Garkha Bypass