MDRRCD BiharCompleted

Improvement work from Chapra- Sonepur Road (Gola Bazar) to Chapra sonepur Road (Dudhaila More) Via Chhoa Mill, Screw Pile Bridge , Najarmira, RaharDiyara, Balli Tola, Sahpur Diyara, Hariharnath- Pahlejaghat and Dudhaila bazar Road (Total Length-6.480 km)

#155
Road Division Sonepur
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹8.68 Cr
Length6.48 km
Start19-05-2020
Completion18-06-2021
MDR · North Wing
Road Division Sonepur
SAURAV RAJ

Project Details

6 Fields
Project No.
155
Wing
North Wing
Division
Road Division Sonepur
Circle
Saran Road Circle Hajipur.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹8.68 Cr
Sanctioned Length
6.48 km
Contractor
SAURAV RAJ
AA Date
25-09-2019
Start Date
19-05-2020
Expected Completion
18-06-2021

Improvement work from Chapra- Sonepur Road (Gola Bazar) to Chapra sonepur Road (Dudhaila More) Via Chhoa Mill, Screw Pile Bridge , Najarmira, RaharDiyara, Balli Tola, Sahpur Diyara, Hariharnath- Pahlejaghat and Dudhaila bazar Road (Total Length-6.480 km) is a Bihar Road Construction Department (RCD) project under Road Division Sonepur, classified as a MDR. The agreement amount for this project is ₹8.68 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

work completed.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Improvement work from Chapra- Sonepur Road (Gola Bazar) to Chapra sonepur Road ("?
Status: Completed. This MDR project under Road Division Sonepur (Saran Road Circle Hajipur.) covers 6.48 km of road work. Expected completion: 18-06-2021.
QWho is the contractor for RCD project 155?
The contractor for this project is SAURAV RAJ. Project number: 155. Division: Road Division Sonepur. Administrative approval date: 25-09-2019.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Improvement work from Chapra- Sonepur Road (Gola Bazar) to C" is ₹8.68 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Sonepur.
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 155 "Improvement work from Chapra- Sonepur Road (Gola Bazar) to C" is one of thousands of road improvement and construction works tracked by BiharInfraTales.