MDRRCD BiharCompleted

Widening / Strengthening of Malahi More(Bhaiya Bigha) to Gendupur (Mahauri Road) including culverts & minor bridges. Length – 12.410 km (Package No-.BR12RC-345)

#535
Road Division Gaya.
Magadh Road Circle Gaya
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹11.78 Cr
Length12.41 km
Start15-11-2022
Completion31-12-2023
MDR · South Wing
Road Division Gaya.
M/s Maa Komli Construction

Project Details

6 Fields
Project No.
535
Wing
South Wing
Division
Road Division Gaya.
Circle
Magadh Road Circle Gaya
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹11.78 Cr
Sanctioned Length
12.41 km
Contractor
M/s Maa Komli Construction
AA Date
30-09-2022
Start Date
15-11-2022
Expected Completion
31-12-2023

Widening / Strengthening of Malahi More(Bhaiya Bigha) to Gendupur (Mahauri Road) including culverts & minor bridges. Length – 12.410 km (Package No-.BR12RC-345) is a Bihar Road Construction Department (RCD) project under Road Division Gaya., classified as a MDR. The agreement amount for this project is ₹11.78 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Construction work completed except 250m road length due to land dispute. . NOC granted by RWD, Patna vide letter no. 4687 dated 22.08.2023 in disputed road portion. EOT granted upto 14.11.2023. 242 m drain constructed.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Widening / Strengthening of Malahi More(Bhaiya Bigha) to Gendupur (Mahauri Road)"?
Status: Completed. This MDR project under Road Division Gaya. (Magadh Road Circle Gaya) covers 12.41 km of road work. Expected completion: 31-12-2023.
QWho is the contractor for RCD project 535?
The contractor for this project is M/s Maa Komli Construction. Project number: 535. Division: Road Division Gaya.. Administrative approval date: 30-09-2022.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Widening / Strengthening of Malahi More(Bhaiya Bigha) to Gen" is ₹11.78 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gaya..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 535 "Widening / Strengthening of Malahi More(Bhaiya Bigha) to Gen" is one of thousands of road improvement and construction works tracked by BiharInfraTales.