MDRRCD BiharCompleted
W/S of 2nd km of atri- jethian road to Saren via Punar - kariyat - Manjhauli - Bandi including culverts & minor bridges RCPLWEA Package No- BR12RC307
#530
Road Division Gaya.
Magadh Road Circle Gaya
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹14.74 Cr
Length14.50 km
Start14-10-2022
Completion31-03-2026
MDR · South Wing
Road Division Gaya.
Mukesh Kumar
Project Details
6 FieldsProject No.
530
Wing
South Wing
Division
Road Division Gaya.
Circle
Magadh Road Circle Gaya
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹14.74 Cr
Sanctioned Length
14.50 km
Contractor
Mukesh Kumar
AA Date
02-02-2022
Start Date
14-10-2022
Expected Completion
31-03-2026
W/S of 2nd km of atri- jethian road to Saren via Punar - kariyat - Manjhauli - Bandi including culverts & minor bridges RCPLWEA Package No- BR12RC307 is a Bihar Road Construction Department (RCD) project under Road Division Gaya., classified as a MDR. The agreement amount for this project is ₹14.74 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
work completed..
SE Inspection Log
Superintending Engineer quality visit record
Magadh Road Circle Gaya · Road Division Gaya.
Visited: 18 Feb 2025"
"Attached Report"
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "W/S of 2nd km of atri- jethian road to Saren via Punar - kariyat - Manjhauli - B"?
- Status: Completed. This MDR project under Road Division Gaya. (Magadh Road Circle Gaya) covers 14.50 km of road work. Expected completion: 31-03-2026.
- QWho is the contractor for RCD project 530?
- The contractor for this project is Mukesh Kumar. Project number: 530. Division: Road Division Gaya.. Administrative approval date: 02-02-2022.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "W/S of 2nd km of atri- jethian road to Saren via Punar - kar" is ₹14.74 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gaya..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 530 "W/S of 2nd km of atri- jethian road to Saren via Punar - kar" is one of thousands of road improvement and construction works tracked by BiharInfraTales.