MDRRCD BiharCompleted

Construction of RCC Drain & PCC Road both side of Kudra ROB & 1st km in Kudra-Bhabua Road for the year 2018-19

#518
Road Division Bhabhua.
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹2.49 Cr
Length2.05 km
Start12-02-2019
Completion15-01-2023
MDR · South Wing
Road Division Bhabhua.
Balwant Const Pvt. Ltd.

Project Details

6 Fields
Project No.
518
Wing
South Wing
Division
Road Division Bhabhua.
Circle
Bhojpur Road Circle Arrah.
Road Type
MDR
Head
Non Plan

Cost & Timeline

6 Fields
Agreement Value
₹2.49 Cr
Sanctioned Length
2.05 km
Contractor
Balwant Const Pvt. Ltd.
AA Date
03-10-2018
Start Date
12-02-2019
Expected Completion
15-01-2023

Construction of RCC Drain & PCC Road both side of Kudra ROB & 1st km in Kudra-Bhabua Road for the year 2018-19 is a Bihar Road Construction Department (RCD) project under Road Division Bhabhua., classified as a MDR. The agreement amount for this project is ₹2.49 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

1.57 KM drain Work completed. 481 M drain descoped via letter no. 2510 (E) dated 06.05.2022

SE Inspection Log

Superintending Engineer quality visit record

Bhojpur Road Circle Arrah. · Road Division Bhabhua.

Visited: 13 Aug 2024
"

"इस पथ की कुल लम्बाई 20.00 कि०मी० एवं चौड़ाई 5.5 मी0 है जिसमें पथ प्रमंडल, भभुआ अन्तर्गत चैनेज 0.00 से 20.00 कि0मी0 तक है। इस पथ का संधारण OPRMC Package No. 35A (M/s Brijendra Singh) के अन्तर्गत किया जा रहा है। निरीक्षण के क्रम में पथ संतोषजनक पाया गया।"

Inspection Report PDF
?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Construction of RCC Drain & PCC Road both side of Kudra ROB & 1st km in Kudra-Bh"?
Status: Completed. This MDR project under Road Division Bhabhua. (Bhojpur Road Circle Arrah.) covers 2.05 km of road work. Expected completion: 15-01-2023.
QWho is the contractor for RCD project 518?
The contractor for this project is Balwant Const Pvt. Ltd.. Project number: 518. Division: Road Division Bhabhua.. Administrative approval date: 03-10-2018.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Construction of RCC Drain & PCC Road both side of Kudra ROB " is ₹2.49 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Bhabhua..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 518 "Construction of RCC Drain & PCC Road both side of Kudra ROB " is one of thousands of road improvement and construction works tracked by BiharInfraTales.