Construction of RCC Longitudinal Drain in Ramgarh Durgawati Road at Devhaliya Bazar in KM 10 & 11P for the year 2025-26 Under Road Division Bhabua
#1129
Road Division Bhabhua.
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹2.65 Cr
Length3.00 km
Start06-10-2025
Completion05-07-2026
MDR · South Wing
Road Division Bhabhua.
MANISH VINOD SINGH CONSTRUCTION (PROP-MANISH KUMAR SINGH)
Project Details
Project No.1129
WingSouth Wing
DivisionRoad Division Bhabhua.
CircleBhojpur Road Circle Arrah.
Road TypeMDR
HeadState Plan
Cost & Timeline
Agreement Value₹2.65 Cr
Sanctioned Length3.00 km
ContractorMANISH VINOD SINGH CONSTRUCTION (PROP-MANISH KUMAR SINGH)
AA Date27-06-2025
Start Date06-10-2025
Expected Completion05-07-2026
Construction of RCC Longitudinal Drain in Ramgarh Durgawati Road at Devhaliya Bazar in KM 10 & 11P for the year 2025-26 Under Road Division Bhabua is a Bihar Road Construction Department (RCD) project under Road Division Bhabhua., classified as a MDR. The agreement amount for this project is ₹2.65 Cr, and the current status is Ongoning.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work is in Progress, Work is delayed due to interruption of local villagers for discharge point of drain
Frequently Asked Questions
- What is the current status of the Bihar RCD project "Construction of RCC Longitudinal Drain in Ramgarh Durgawati Road at Devhaliya Ba"?
- Status: Ongoning. This MDR project under Road Division Bhabhua. (Bhojpur Road Circle Arrah.) covers 3.00 km of road work. Expected completion: 05-07-2026.
- Who is the contractor for RCD project 1129?
- The contractor for this project is MANISH VINOD SINGH CONSTRUCTION (PROP-MANISH KUMAR SINGH). Project number: 1129. Division: Road Division Bhabhua.. Administrative approval date: 27-06-2025.
- What is the agreement value for this Bihar road project?
- The agreement value for "Construction of RCC Longitudinal Drain in Ramgarh Durgawati " is ₹2.65 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Bhabhua..
- What does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 1129 "Construction of RCC Longitudinal Drain in Ramgarh Durgawati " is one of thousands of road improvement and construction works tracked by BiharInfraTales.