Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /RCD PMIS
  3. /Construction of Indo-Nepal Border Road Project und
MDRRCD BiharCompleted

Construction of Indo-Nepal Border Road Project under Road Division Bettiah From Bhangaha to Dhutaha River Ch-81.900-112.898)

#516
Road Division Bettiah.
Road Circle Motihari
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹116.09 Cr
Length31.00 km
Start08-07-2019
Completion30-04-2025
MDR · North Wing
Road Division Bettiah.
M/s Sri Ram Enterprises

Project Details

Project No.516
WingNorth Wing
DivisionRoad Division Bettiah.
CircleRoad Circle Motihari
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹116.09 Cr
Sanctioned Length31.00 km
ContractorM/s Sri Ram Enterprises
AA Date14-02-2017
Start Date08-07-2019
Expected Completion30-04-2025

Remarks

Work Completed

SE Inspection Log

Superintending Engineer quality visit record

Road Circle Motihari · Road Division Bettiah.

Visited: 29 Aug 2024
"

"GSB-27.90km, WMM-26.50km, DBM-25.90km & SDBC-22.90km work has been done. In Ch.-17.500 to 18.700 km E/W progress is slow. In Ch.-26.100 to 27.200km WMM 1st layer work is in progress."

Inspection Report PDF

Frequently Asked Questions

What is the current status of the Bihar RCD project "Construction of Indo-Nepal Border Road Project under Road Division Bettiah From "?
Status: Completed. This MDR project under Road Division Bettiah. (Road Circle Motihari) covers 31.00 km of road work. Expected completion: 30-04-2025.
Who is the contractor for RCD project 516?
The contractor for this project is M/s Sri Ram Enterprises. Project number: 516. Division: Road Division Bettiah.. Administrative approval date: 14-02-2017.
What is the agreement value for this Bihar road project?
The agreement value for "Construction of Indo-Nepal Border Road Project under Road Di" is ₹116.09 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Bettiah..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 516 "Construction of Indo-Nepal Border Road Project under Road Di" is one of thousands of road improvement and construction works tracked by BiharInfraTales.
Bihar RCD PMIS Dashboard

Related Resources

RCD

Bihar RCD PMIS Dashboard

All RCD road projects across Bihar

Roads

Bihar Road Network GIS Map

Visual map of Bihar highway and road network

NHAI

NHAI Drone Tracker

National highway drone-monitored progress

BRPNNL

BRPNNL Bridge Projects

Bihar bridge project monitor

Projects

Bihar Infrastructure Projects

All government infrastructure project tracker

Tenders

Bihar Government Tenders

Active procurement notices for road projects

IPM

Central Project Monitor (IPM)

Centrally-funded infrastructure in Bihar

Cabinet

Bihar Cabinet Decisions

Government policy for infrastructure projects

EC

Stage-1 EC Clearances

Forest and environmental clearances

Districts

Bihar District Data

District-level infrastructure and demographics

  1. BiharInfraTales
  2. /RCD PMIS
  3. /Construction of Indo-Nepal Border Road Project und