| Project No. | 513 |
| Wing | North Wing |
| Division | Road Division Bettiah. |
| Circle | Road Circle Motihari |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹101.61 Cr |
| Sanctioned Length | 26.50 km |
| Contractor | Ujjain Engicon India Pvt. Ltd. |
| AA Date | 14-02-2017 |
| Start Date | 08-07-2019 |
| Expected Completion | 30-06-2025 |
Work Completed
Superintending Engineer quality visit record
Road Circle Motihari · Road Division Bettiah.
Visited: 29 Dec 2023"During inspection E/W-22Km, GSB-17Km, WMM-9Km was found completed and E/W & GSB Work was in progress in the remaining stretches. Box Culvert & HP Culvert work was in progress. No Bituminous work was found in progress. In this regards the officers & agency present there was directed to start the Bituminous work & remaining other works at the earliest. Contractor representative said that installation of HOT Mix Plat is in progress which likely to be completed in 10 to 15 days after that bituminous work will be started."