MDRRCD BiharCompleted

W/S (from intermediate lane to double lane) of Muzaffarpur to Mahua road (km 0.00 to km 14.30) under PMGSY (PCPLWE) in district of Muzaffarpur,Bihar for the year 2017-18 (Package NO.BR23RC-103

#461
Road Division Muzaffarpur -1
North Bihar Road Circle Muzaffarpur
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹15.61 Cr
Length14.30 km
Start13-12-2018
Completion12-06-2020
MDR · North Wing
Road Division Muzaffarpur -1
RAI RAJ CONSTRUCTION PRIVATE LIMITED

Project Details

6 Fields
Project No.
461
Wing
North Wing
Division
Road Division Muzaffarpur -1
Circle
North Bihar Road Circle Muzaffarpur
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹15.61 Cr
Sanctioned Length
14.30 km
Contractor
RAI RAJ CONSTRUCTION PRIVATE LIMITED
AA Date
02-07-2018
Start Date
13-12-2018
Expected Completion
12-06-2020

W/S (from intermediate lane to double lane) of Muzaffarpur to Mahua road (km 0.00 to km 14.30) under PMGSY (PCPLWE) in district of Muzaffarpur,Bihar for the year 2017-18 (Package NO.BR23RC-103 is a Bihar Road Construction Department (RCD) project under Road Division Muzaffarpur -1, classified as a MDR. The agreement amount for this project is ₹15.61 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Road work completed

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "W/S (from intermediate lane to double lane) of Muzaffarpur to Mahua road (km 0.0"?
Status: Completed. This MDR project under Road Division Muzaffarpur -1 (North Bihar Road Circle Muzaffarpur) covers 14.30 km of road work. Expected completion: 12-06-2020.
QWho is the contractor for RCD project 461?
The contractor for this project is RAI RAJ CONSTRUCTION PRIVATE LIMITED. Project number: 461. Division: Road Division Muzaffarpur -1. Administrative approval date: 02-07-2018.
QWhat is the agreement value for this Bihar road project?
The agreement value for "W/S (from intermediate lane to double lane) of Muzaffarpur t" is ₹15.61 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Muzaffarpur -1.
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 461 "W/S (from intermediate lane to double lane) of Muzaffarpur t" is one of thousands of road improvement and construction works tracked by BiharInfraTales.