| Project No. | 297 |
| Wing | South Wing |
| Division | Road Division Gaya. |
| Circle | Magadh Road Circle Gaya |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹9.03 Cr |
| Sanctioned Length | 9.04 km |
| Contractor | M/s Sidhnath Construction |
| AA Date | 15-02-2019 |
| Start Date | 20-08-2019 |
| Expected Completion | 19-06-2020 |
Work completed. In this road work of 660m length in 1st & 2nd km have not completed in Bara Village due to objection occurred by local villagers. Therefore as per guidence of higher authority this portion of road will be descoped from the from the total project length. In this regarding letter for descope of 660m from the total project length