Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

Construction of Widening and Strengthening of NH-83 Chakand Gumti - Pretshila to Kujapi (SH-07) road for the year 2018-19. (Package No. - BR12RC48)

#297
Road Division Gaya.
Magadh Road Circle Gaya
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹9.03 Cr
Length9.04 km
Start20-08-2019
Completion19-06-2020
MDR · South Wing
Road Division Gaya.
M/s Sidhnath Construction

Project Details

Project No.297
WingSouth Wing
DivisionRoad Division Gaya.
CircleMagadh Road Circle Gaya
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹9.03 Cr
Sanctioned Length9.04 km
ContractorM/s Sidhnath Construction
AA Date15-02-2019
Start Date20-08-2019
Expected Completion19-06-2020

Construction of Widening and Strengthening of NH-83 Chakand Gumti - Pretshila to Kujapi (SH-07) road for the year 2018-19. (Package No. - BR12RC48) is a Bihar Road Construction Department (RCD) project under Road Division Gaya., classified as a MDR. The agreement amount for this project is ₹9.03 Cr, and the current status is **Completed**.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work completed. In this road work of 660m length in 1st & 2nd km have not completed in Bara Village due to objection occurred by local villagers. Therefore as per guidence of higher authority this portion of road will be descoped from the from the total project length. In this regarding letter for descope of 660m from the total project length

Frequently Asked Questions

What is the current status of the Bihar RCD project "Construction of Widening and Strengthening of NH-83 Chakand Gumti - Pretshila to"?
Status: Completed. This MDR project under Road Division Gaya. (Magadh Road Circle Gaya) covers 9.04 km of road work. Expected completion: 19-06-2020.
Who is the contractor for RCD project 297?
The contractor for this project is M/s Sidhnath Construction. Project number: 297. Division: Road Division Gaya.. Administrative approval date: 15-02-2019.
What is the agreement value for this Bihar road project?
The agreement value for "Construction of Widening and Strengthening of NH-83 Chakand " is ₹9.03 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gaya..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 297 "Construction of Widening and Strengthening of NH-83 Chakand " is one of thousands of road improvement and construction works tracked by BiharInfraTales.