| Project No. | 264 |
| Wing | South Wing |
| Division | Road Division Patna City. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹69.57 Cr |
| Sanctioned Length | 18.20 km |
| Contractor | BABA HANS CONST. PVT. LTD. |
| AA Date | 01-09-2020 |
| Start Date | 09-04-2021 |
| Expected Completion | 08-04-2023 |
Work completed on 02.11.2024 HL Bridge CH-1+200 (7x12m) completed CH-2+200 (5x10m)- Completed. 4+225 (3x16m)- Completed, 5+700 (7x10m)- Completed.
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Patna City.
Visited: 25 Jul 2024"During inspection, the progress of road work was found satisfactory. Instructions were given to the concerned engineer and contractor to speed up the bridge construction work and complete the work as soon as possible."