Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

OLD GT Road (Double Lane to 4- Lane/6-Lane) from KM(CH. 0.000 to CH. 8.280) under CRF

#135
Road Division Kochas
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹43.74 Cr
Length8.28 km
Start18-09-2020
Completion31-05-2023
MDR · South Wing
Road Division Kochas
R.B.A Construction Pvt. Ltd.

Project Details

Project No.135
WingSouth Wing
DivisionRoad Division Kochas
CircleBhojpur Road Circle Arrah.
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹43.74 Cr
Sanctioned Length8.28 km
ContractorR.B.A Construction Pvt. Ltd.
AA Date02-11-2018
Start Date18-09-2020
Expected Completion31-05-2023

OLD GT Road (Double Lane to 4- Lane/6-Lane) from KM(CH. 0.000 to CH. 8.280) under CRF is a Bihar Road Construction Department (RCD) project under Road Division Kochas, classified as a MDR. The agreement amount for this project is ₹43.74 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work completed.

Frequently Asked Questions

What is the current status of the Bihar RCD project "OLD GT Road (Double Lane to 4- Lane/6-Lane) from KM(CH. 0.000 to CH. 8.280) unde"?
Status: Completed. This MDR project under Road Division Kochas (Bhojpur Road Circle Arrah.) covers 8.28 km of road work. Expected completion: 31-05-2023.
Who is the contractor for RCD project 135?
The contractor for this project is R.B.A Construction Pvt. Ltd.. Project number: 135. Division: Road Division Kochas. Administrative approval date: 02-11-2018.
What is the agreement value for this Bihar road project?
The agreement value for "OLD GT Road (Double Lane to 4- Lane/6-Lane) from KM(CH. 0.00" is ₹43.74 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Kochas.
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 135 "OLD GT Road (Double Lane to 4- Lane/6-Lane) from KM(CH. 0.00" is one of thousands of road improvement and construction works tracked by BiharInfraTales.