CONSTRUCTION OF UBHAVAN TO NUAOWROAD FROM KM 0.00 TO KM 1.98 (PACKAGE NO.-BR28RC147)
#1334
Road Division Kochas
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹2.03 Cr
Length1.98 km
Start28-01-2021
Completion27-07-2021
MDR · South Wing
Road Division Kochas
SATYA NARAYAN SINGH CONSTRUCTION PVT. LTD.
Project Details
Project No.1334
WingSouth Wing
DivisionRoad Division Kochas
CircleBhojpur Road Circle Arrah.
Road TypeMDR
HeadState Plan
Cost & Timeline
Agreement Value₹2.03 Cr
Sanctioned Length1.98 km
ContractorSATYA NARAYAN SINGH CONSTRUCTION PVT. LTD.
AA Date31-08-2020
Start Date28-01-2021
Expected Completion27-07-2021
CONSTRUCTION OF UBHAVAN TO NUAOWROAD FROM KM 0.00 TO KM 1.98 (PACKAGE NO.-BR28RC147) is a Bihar Road Construction Department (RCD) project under Road Division Kochas, classified as a MDR. The agreement amount for this project is ₹2.03 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Frequently Asked Questions
- What is the current status of the Bihar RCD project "CONSTRUCTION OF UBHAVAN TO NUAOWROAD FROM KM 0.00 TO KM 1.98 (PACKAGE NO.-BR28RC"?
- Status: Completed. This MDR project under Road Division Kochas (Bhojpur Road Circle Arrah.) covers 1.98 km of road work. Expected completion: 27-07-2021.
- Who is the contractor for RCD project 1334?
- The contractor for this project is SATYA NARAYAN SINGH CONSTRUCTION PVT. LTD.. Project number: 1334. Division: Road Division Kochas. Administrative approval date: 31-08-2020.
- What is the agreement value for this Bihar road project?
- The agreement value for "CONSTRUCTION OF UBHAVAN TO NUAOWROAD FROM KM 0.00 TO KM 1.98" is ₹2.03 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Kochas.
- What does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 1334 "CONSTRUCTION OF UBHAVAN TO NUAOWROAD FROM KM 0.00 TO KM 1.98" is one of thousands of road improvement and construction works tracked by BiharInfraTales.