East Central RailwayIn Progress

Transportation of P.way material's & Track linking works from CH:72900.00 to Madhubani yard in connection with construction of Hajipur-Sagauli new BG rail line project

Work #289
As of June 2026

Estimate Cost

₹40.31 Cr

Sanctioned estimate

Tendered Cost

₹38.78 Cr

-3.8% vs estimate

Physical Progress

15%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹38.78 Cr
Progress15%
Started04-10-2023
Target DOC31-08-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
289
Agency
NNT Developers Private Limited-Patna
104, Sri Ram Tower, Kankarbagh, Patna-800021
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-15-23-24/01540740088169 dt 04.10.23
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹40.31 Cr
Tendered Cost
₹38.78 Cr
Physical Progress
15%
Date Started
04-10-2023
Original DOC
03-09-2024
Extended DOC
31-08-2026

Transportation of P.way material's & Track linking works from CH:72900.00 to Madhubani yard in connection with construction of Hajipur-Sagauli new BG rail line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s NNT Developers Private Limited-Patna. The tendered cost of the work is ₹38.78 Cr, and it is currently In Progress with physical progress recorded at 15%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Transportation of P.way material's & Track linking works from CH:72900.00 to Mad"?
Status: In Progress. This East Central Railway work is being executed by M/s NNT Developers Private Limited-Patna. Physical progress stands at 15%. Current date of completion (DOC): 31-08-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s NNT Developers Private Limited-Patna, 104, Sri Ram Tower, Kankarbagh, Patna-800021. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-15-23-24/01540740088169 dt 04.10.23. Work started on 04-10-2023.
QWhat is the cost of this railway work?
The tendered cost of "Transportation of P.way material's & Track linking works fro" is ₹38.78 Cr (against an estimate of ₹40.31 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Transportation of P.way material's & Track linking works fro" is one of hundreds of railway works covered.