East Central RailwayCompleted

Supplying fabrication, erection and launching of 45.7m OWG for (Br. No. 13, 33, 41, 92), 30.5m OWG for (Br. No. 99, 107, 111, 118, 121A), fixing of bearing and other associate work in connection with gauge conversion work of Saharsa-Forbesganj section of Samastipur Division of East Central Railway.

Work #208
As of June 2026

Estimate Cost

₹16.91 Cr

Sanctioned estimate

Tendered Cost

₹19.49 Cr

+15.3% vs estimate

Physical Progress

100%

Work completed

Status

Completed

Current stage

East Central Railway — CAO (Con)Completed
Tendered₹19.49 Cr
Progress100%
Started05-06-2020
Target DOC30-06-2023
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG

Work Details

5 Fields
Work No.
208
Acceptance / LOA
ECR-CAO-C-N-ETN-85-19-20/853600015328 Dtd 10/02/2020; ECR/CAO/Con/WT/Agt/147 Dtd 28.12.2020
Officer in Charge
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹16.91 Cr
Tendered Cost
₹19.49 Cr
Physical Progress
100%
Date Started
05-06-2020
Original DOC
30-06-2023
Extended DOC
N/A

Supplying fabrication, erection and launching of 45.7m OWG for (Br. No. 13, 33, 41, 92), 30.5m OWG for (Br. No. 99, 107, 111, 118, 121A), fixing of bearing and other associate work in connection with gauge conversion work of Saharsa-Forbesganj section of Samastipur Division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s BRBA Infratech LLP. The tendered cost of the work is ₹19.49 Cr, and it is currently Completed with physical progress recorded at 100%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supplying fabrication, erection and launching of 45.7m OWG for (Br. No. 13, 33, "?
Status: Completed. This East Central Railway work is being executed by M/s BRBA Infratech LLP. Physical progress stands at 100%. Current date of completion (DOC): 30-06-2023.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s BRBA Infratech LLP. Acceptance / agreement reference: ECR-CAO-C-N-ETN-85-19-20/853600015328 Dtd 10/02/2020; ECR/CAO/Con/WT/Agt/147 Dtd 28.12.2020. Work started on 05-06-2020.
QWhat is the cost of this railway work?
The tendered cost of "Supplying fabrication, erection and launching of 45.7m OWG f" is ₹19.49 Cr (against an estimate of ₹16.91 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying fabrication, erection and launching of 45.7m OWG f" is one of hundreds of railway works covered.