Supply, stacking and spreading of stone ballast, linking of permanent way including transportation of P.Way materials like Rail, Sleeper, fittings etc and other associated work as per Railway's specifications and standards in connection with construction of permanent Diversion on major bridges between Saraigarh-Forbesganj section in Samastipur Division of East Central Railway.
Estimate Cost
₹5.69 Cr
Sanctioned estimate
Tendered Cost
₹5.69 Cr
0.0% vs estimate
Physical Progress
81%
Work completed
Status
Overdue
Past target DOC
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsSupply, stacking and spreading of stone ballast, linking of permanent way including transportation of P.Way materials like Rail, Sleeper, fittings etc and other associated work as per Railway's specifications and standards in connection with construction of permanent Diversion on major bridges between Saraigarh-Forbesganj section in Samastipur Division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s M K Engineering-Guwahati. The tendered cost of the work is ₹5.69 Cr, and it is currently Overdue with physical progress recorded at 81%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Frequently Asked Questions
- QWhat is the current status of the railway work "Supply, stacking and spreading of stone ballast, linking of permanent way includ"?
- Status: Overdue (overdue). This East Central Railway work is being executed by M/s M K Engineering-Guwahati. Physical progress stands at 81%. Current date of completion (DOC): 09-06-2025.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/s M K Engineering-Guwahati, West Maligaon, Guwahati-781011, Assam, India. Acceptance / agreement reference: ECR-CAO-C-N-ETN-40-23-24/01112730089991 Dated 30/10/2023; ECR/ECRC/Civil/2023/0063 Dt 08.02.2024. Work started on 28-11-2023.
- QWhat is the cost of this railway work?
- The tendered cost of "Supply, stacking and spreading of stone ballast, linking of " is ₹5.69 Cr (against an estimate of ₹5.69 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supply, stacking and spreading of stone ballast, linking of " is one of hundreds of railway works covered.