East Central RailwayIn Progress

Construction of sub-structure of major bridge No. 14 & 15 on well foundation and earth work in filling and blanketing from Km.15.0 to 21.0 between KSP-HYT in connection with SPJ-DBG doubling.

Work #11
As of March 2026

Estimate Cost

₹44.75 Cr

Sanctioned estimate

Tendered Cost

₹53.92 Cr

+20.5% vs estimate

Physical Progress

70%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹53.92 Cr
Progress70%
Started29-04-2018
Target DOC30-06-2026
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ

Work Details

5 Fields
Work No.
11
Agency
Acceptance / LOA
ECR/CAO/C/N/ETN-35-16-17 Dt 15.06.2017 ** ECR/CAO/Con/WT/Agt/35 dt.19.01.2018
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹44.75 Cr
Tendered Cost
₹53.92 Cr
Physical Progress
70%
Date Started
29-04-2018
Original DOC
14-12-2018
Extended DOC
30-06-2026

Construction of sub-structure of major bridge No. 14 & 15 on well foundation and earth work in filling and blanketing from Km.15.0 to 21.0 between KSP-HYT in connection with SPJ-DBG doubling. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Hari-GPT (JV) At & PO Keshawe. The tendered cost of the work is ₹53.92 Cr, and it is currently In Progress with physical progress recorded at 70%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

work In progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of sub-structure of major bridge No. 14 & 15 on well foundation and"?
Status: In Progress. This East Central Railway work is being executed by Hari-GPT (JV) At & PO Keshawe. Physical progress stands at 70%. Current date of completion (DOC): 30-06-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Hari-GPT (JV) At & PO Keshawe, Distt-Begusarai.. Acceptance / agreement reference: ECR/CAO/C/N/ETN-35-16-17 Dt 15.06.2017 ** ECR/CAO/Con/WT/Agt/35 dt.19.01.2018. Work started on 29-04-2018.
QWhat is the cost of this railway work?
The tendered cost of "Construction of sub-structure of major bridge No. 14 & 15 on" is ₹53.92 Cr (against an estimate of ₹44.75 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of sub-structure of major bridge No. 14 & 15 on" is one of hundreds of railway works covered.