East Central RailwayNot Started

Construction of Station building, Service building, S&T buildings, Electrical buildings, Residential Qtrs., Approach road, High level Platform, PP shed, FOB, Circulating area, Height gauge and other Miscellaneous works between Raniganj-Jadia section (i.e. Km 28.000 to Km 51.800) in connection with new rail line project of Araria-Supaul in Samastipur division of East Central Railway.

Estimate Cost

₹100.08 Cr

Sanctioned estimate

Tendered Cost

₹91.43 Cr

-8.6% vs estimate

Physical Progress

0%

Work completed

Status

Not Started

Current stage

East Central Railway — CAO (Con)Not Started
Tendered₹91.43 Cr
Progress0%
Started11-09-2025
Target DOC30-06-2026
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG

Work Details

5 Fields
Work No.
230
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-32-23-24/00873270099377; ECR/ECRC/Civil/2024/0057
Officer in Charge
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; A K Sinha, AEN/C/DBG
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹100.08 Cr
Tendered Cost
₹91.43 Cr
Physical Progress
0%
Date Started
11-09-2025
Original DOC
30-06-2026
Extended DOC
N/A

Construction of Station building, Service building, S&T buildings, Electrical buildings, Residential Qtrs., Approach road, High level Platform, PP shed, FOB, Circulating area, Height gauge and other Miscellaneous works between Raniganj-Jadia section (i.e. Km 28.000 to Km 51.800) in connection with new rail line project of Araria-Supaul in Samastipur division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Hari Construction and Associated Private Limited-Begusarai. The tendered cost of the work is ₹91.43 Cr, and it is currently Not Started with physical progress recorded at 0%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Station building, Service building, S&T buildings, Electrical bu"?
Status: Not Started. This East Central Railway work is being executed by M/s Hari Construction and Associated Private Limited-Begusarai. Physical progress stands at 0%. Current date of completion (DOC): 30-06-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Hari Construction and Associated Private Limited-Begusarai. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-32-23-24/00873270099377; ECR/ECRC/Civil/2024/0057. Work started on 11-09-2025.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Station building, Service building, S&T buil" is ₹91.43 Cr (against an estimate of ₹100.08 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Station building, Service building, S&T buil" is one of hundreds of railway works covered.