East Central RailwayIn Progress

Construction of Station building, Service building, S & T buildings, Electrical buildings, Residential Qtrs, Approach road, High level Platform, Wharf, PP shed, FOB, Circulating area, Height gauge and other Miscellaneous works between Araria-Raniganj section (i.e. Km 00.00 to Km 28.00) in connection with new rail line project of Araria Supaul in Samastipur division of East Central Railway.

Work #239
As of June 2026

Estimate Cost

₹121.52 Cr

Sanctioned estimate

Tendered Cost

N/A

Awarded value

Physical Progress

3%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
TenderedN/A
Progress3%
Started25-11-2024
Target DOC08-07-2027
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; H R Chaudhary, AEN/C/SRGR

Work Details

5 Fields
Work No.
239
Agency
JPW Infratech Private Limited
Korba, A1 Shyama Enclave TP Nagar, Chhattisgarh-495677
Acceptance / LOA
CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-25-23-24/01049260107312 Dtd 08/07/2024; ECR/ECRC/Civil/2024/00101 Dated 20/11/2024
Officer in Charge
Satya Prakash Yadav, CE/C/N/MHX; Pankaj Kr, Dy CE/C/III/SPJ; H R Chaudhary, AEN/C/SRGR
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹121.52 Cr
Tendered Cost
N/A
Physical Progress
3%
Date Started
25-11-2024
Original DOC
08-07-2027
Extended DOC
N/A

Construction of Station building, Service building, S & T buildings, Electrical buildings, Residential Qtrs, Approach road, High level Platform, Wharf, PP shed, FOB, Circulating area, Height gauge and other Miscellaneous works between Araria-Raniganj section (i.e. Km 00.00 to Km 28.00) in connection with new rail line project of Araria Supaul in Samastipur division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by JPW Infratech Private Limited. it is currently In Progress with physical progress recorded at 3%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Station building, Service building, S & T buildings, Electrical "?
Status: In Progress. This East Central Railway work is being executed by JPW Infratech Private Limited. Physical progress stands at 3%. Current date of completion (DOC): 08-07-2027.
QWho is the agency for this Bihar railway project?
The agency for this work is JPW Infratech Private Limited, Korba, A1 Shyama Enclave TP Nagar, Chhattisgarh-495677. Acceptance / agreement reference: CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-25-23-24/01049260107312 Dtd 08/07/2024; ECR/ECRC/Civil/2024/00101 Dated 20/11/2024. Work started on 25-11-2024.
QWhat is the cost of this railway work?
Tendered cost details are not available in the current dataset for this railway work. Please refer to the official East Central Railway records.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Station building, Service building, S & T bu" is one of hundreds of railway works covered.