East Central RailwayIn Progress

Construction of S & R building, Passenger amenities and other Miscellaneous work i.e. Providing and fixing, Lifting Barrier at level crossing, Construction of Gate Lodge, Staff Quarters, Platform, Platform Shed, FOB, approach Road at Stations & Level Crossings etc, between Kakarghati-Shisho stations in connection with a new Bye-Pass Line from Kakarghati to Shisho (excluding Darbhanga Junction)

Work #171
As of June 2026

Estimate Cost

N/A

Sanctioned estimate

Tendered Cost

₹26.91 Cr

Awarded value

Physical Progress

80%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹26.91 Cr
Progress80%
Started11-12-2020
Target DOC31-10-2026
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ

Work Details

5 Fields
Work No.
171
Agency
R N Jha - Siliguri
Bihat, Ratan Chowk, Begusarai, Bihar, Siliguri-851135, WB, India
Acceptance / LOA
ECR-CAO-C-N-ETN-87-19-20/00863610018914 dt 11/05/20 ** ECR/CAO/Con/WT/Agt/136 dt. 09/10/2020
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/I/SPJ; Rakesh Ranjan, AEN/C/SPJ
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
N/A
Tendered Cost
₹26.91 Cr
Physical Progress
80%
Date Started
11-12-2020
Original DOC
10-05-2021
Extended DOC
31-10-2026

Construction of S & R building, Passenger amenities and other Miscellaneous work i.e. Providing and fixing, Lifting Barrier at level crossing, Construction of Gate Lodge, Staff Quarters, Platform, Platform Shed, FOB, approach Road at Stations & Level Crossings etc, between Kakarghati-Shisho stations in connection with a new Bye-Pass Line from Kakarghati to Shisho (excluding Darbhanga Junction) is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s R N Jha - Siliguri. The tendered cost of the work is ₹26.91 Cr, and it is currently In Progress with physical progress recorded at 80%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of S & R building, Passenger amenities and other Miscellaneous work"?
Status: In Progress. This East Central Railway work is being executed by M/s R N Jha - Siliguri. Physical progress stands at 80%. Current date of completion (DOC): 31-10-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s R N Jha - Siliguri, Bihat, Ratan Chowk, Begusarai, Bihar, Siliguri-851135, WB, India. Acceptance / agreement reference: ECR-CAO-C-N-ETN-87-19-20/00863610018914 dt 11/05/20 ** ECR/CAO/Con/WT/Agt/136 dt. 09/10/2020. Work started on 11-12-2020.
QWhat is the cost of this railway work?
The tendered cost of "Construction of S & R building, Passenger amenities and othe" is ₹26.91 Cr. This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of S & R building, Passenger amenities and othe" is one of hundreds of railway works covered.