East Central RailwayOverdue

Construction of platform, PP shelter, approach road and balance work of station building at Bithan, construction of RUB No.6A & 9A, balance work of minor Bridge No.7,8 & 9 and other miscellaneous work between Hasanpur Road to Bithan in connection with construction of new Railway line between Sakri-Hasanpur Road.

Work #188
As of June 2026

Estimate Cost

₹6.80 Cr

Sanctioned estimate

Tendered Cost

₹7.41 Cr

+9.0% vs estimate

Physical Progress

85%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹7.41 Cr
Progress85%
Started22-11-2018
Target DOC31-12-2025
Mahboob Alam, CE/C/NC/MHX; Avinash Sahani, Dy.CE/C/II/SPJ

Work Details

5 Fields
Work No.
188
Agency
Surendra Prasad Singh
Sarvodaya Nagar, Begusarai
Acceptance / LOA
19.11.2018 / ECR/CAO/Con/WT/Agt/35
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Avinash Sahani, Dy.CE/C/II/SPJ
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹6.80 Cr
Tendered Cost
₹7.41 Cr
Physical Progress
85%
Date Started
22-11-2018
Original DOC
31-12-2025
Extended DOC
N/A

Construction of platform, PP shelter, approach road and balance work of station building at Bithan, construction of RUB No.6A & 9A, balance work of minor Bridge No.7,8 & 9 and other miscellaneous work between Hasanpur Road to Bithan in connection with construction of new Railway line between Sakri-Hasanpur Road. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Surendra Prasad Singh. The tendered cost of the work is ₹7.41 Cr, and it is currently Overdue with physical progress recorded at 85%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 7.41/8.75

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of platform, PP shelter, approach road and balance work of station "?
Status: Overdue (overdue). This East Central Railway work is being executed by M/s Surendra Prasad Singh. Physical progress stands at 85%. Current date of completion (DOC): 31-12-2025.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Surendra Prasad Singh, Sarvodaya Nagar, Begusarai. Acceptance / agreement reference: 19.11.2018 / ECR/CAO/Con/WT/Agt/35. Work started on 22-11-2018.
QWhat is the cost of this railway work?
The tendered cost of "Construction of platform, PP shelter, approach road and bala" is ₹7.41 Cr (against an estimate of ₹6.80 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of platform, PP shelter, approach road and bala" is one of hundreds of railway works covered.