East Central RailwayIn Progress

Construction of new ROB (Damodarpur) between MFP-KVC section in lieu of existing ROB and dismantling of existing ROB in connection with Muzaffarpur-Sugauli doubling project.

Work #267
As of June 2026

Estimate Cost

₹46.21 Cr

Sanctioned estimate

Tendered Cost

₹48.07 Cr

+4.0% vs estimate

Physical Progress

31%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹48.07 Cr
Progress31%
Started20-08-2022
Target DOC30-12-2026
Indrajit Kumar, CE/C/NW/MHX; Avanish Sonu, Dy CE/C/I/HJP; Sri. Ravi Shankar Singh (AEN/Con/MFP-I)

Work Details

5 Fields
Work No.
267
Agency
REL-TCL (JV), Goharua House
19, Patliputra Colony, Patna, Bihar
Acceptance / LOA
LAO No. CAO-C-HQ ENGINEERING/ECR-CAO-C-N-ETN-13-22-23/00866770059124 dated 29.07.2022
Officer in Charge
Indrajit Kumar, CE/C/NW/MHX; Avanish Sonu, Dy CE/C/I/HJP; Sri. Ravi Shankar Singh (AEN/Con/MFP-I)
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹46.21 Cr
Tendered Cost
₹48.07 Cr
Physical Progress
31%
Date Started
20-08-2022
Original DOC
29-07-2023
Extended DOC
30-12-2026

Construction of new ROB (Damodarpur) between MFP-KVC section in lieu of existing ROB and dismantling of existing ROB in connection with Muzaffarpur-Sugauli doubling project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by REL-TCL (JV). The tendered cost of the work is ₹48.07 Cr, and it is currently In Progress with physical progress recorded at 31%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of new ROB (Damodarpur) between MFP-KVC section in lieu of existing"?
Status: In Progress. This East Central Railway work is being executed by REL-TCL (JV). Physical progress stands at 31%. Current date of completion (DOC): 30-12-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is REL-TCL (JV), Goharua House, 19, Patliputra Colony, Patna, Bihar. Acceptance / agreement reference: LAO No. CAO-C-HQ ENGINEERING/ECR-CAO-C-N-ETN-13-22-23/00866770059124 dated 29.07.2022. Work started on 20-08-2022.
QWhat is the cost of this railway work?
The tendered cost of "Construction of new ROB (Damodarpur) between MFP-KVC section" is ₹48.07 Cr (against an estimate of ₹46.21 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of new ROB (Damodarpur) between MFP-KVC section" is one of hundreds of railway works covered.